4.0 INSTALLATION
The Planet Model Phantom arm is designed to be mounted above the immediate work area. Stan-
dard mounting fixtures for Planet Model Phantom are: Ceiling Mount & Wall Mount (specialised
mountings are available on application). In all cases the suggested mounting height (measured at
swivel head) is two metres from floor level, as seen in Fig 1.0.
4.1 CEILING MOUNT
!
WARNING
The qualified electrician who is responsible for the installation of the Phantom must include an isola-
tion switch( all -pole disconnection) in the fixed wiring of the Phantom and a cable tie near the termi-
nal block of the primary(240V) wiring (Phase and Neutral) to secure the cables.
STRUCTURAL LOADS - CEILING MOUNT:
The structural integrity of the mounting surface is the responsability of the installer. Structural loads
are as follows:
Fig. 2.0
4.1.1 MOUNT CEILING PLATE - AND LEVEL
Use the Ceiling Template (found in the centre of this document) to mark out the hole locations for the
ceiling plate.
Fig. 3.0
1. Installer must ensure sufficient structural integrity of the mounting surface (Refer to 3.1).
2. Fix the ceiling plate to the structural ceiling using suitable fixings (to be selected by the installer).
3. It is very important that the installer ensures the mounting plate and collar are level. This will ensure