PLID d1
Operating Manual PLID d1
1002227-EN-04
| 7
Installation
The unit should be secured using 2 M4 pan head screws.
Please note during installation:
}
The unit should be installed in a single mounting area with a protection type of at least
IP54.
}
Make sure that the unit is fixed securely.
}
Protect the cable and connector from mechanical stress by using strain relief.
A mounting bracket is available for control cabinet installation (see
Wiring
Please note:
}
}
Calculation of the max. cable length l
max
in the input circuit:
R
lmax
R
l
/ km
I
max
=
R
lmax
= max. overall cable resistance (see
R
l
/ km = cable resistance/km
}
The cable length between PLID d1 and contact (E-STOP pushbutton or start button)
should be as short as possible.
}
Where one line is to be monitored, only use one PLID d1 and one evaluation device.
Route the line so that it is protected.
Preparing for operation
Connect the PLID d1 to the evaluation device PNOZ e8.1p:
}
Connect terminal X1 to terminal S36 on the PNOZ e8.1p
}
Connect terminal X2 to terminal A2 on the PNOZ e8.1p
The evaluation device PNOZ e8.1p should be wired as described in the unit's operating
manual. Ensure the wiring and EMC requirements of IEC 60204-1 are met.
Connection example with N/C contact (continuous test)