Decommissioning
8
Decommissioning
8.1 Shutting down for longer periods
Before shutting down the pump, observe the following procedure and adequately
protect the pump system against corrosion:
Switch off pump.
Change operating fluid
.
Start the pump and allow the pump to warm up.
Fill up the pump with new operating fluid to the top edge of the sightglass.
Close vacuum flange and exhaust flange with locking caps.
8.2 Re-starting
Visually inspect the inner of the pump before taking it into operation. If there is ev-
idence of rust on the parts of the pump which form the housing, then do not take
it into operation and contact Pfeiffer Vacuum Service.
In accordance with DIN 7716 and the manufacturer's specifications we recommend
replacing the installed elastomer parts after 2 years.
If drying pearls were inserted then they should be removed now. Improper
handling can cause failure of the pump.
8.3 Disposal
Products or parts thereof (mechanical and electrical components, operating fluids,
etc.) may cause environmental burden.
Safely dispose of the materials according to the locally applicable regulations.
9
Malfunctions
Please note the following instructions should the pump malfunction:
CAUTION
Emission of operating fluid!
Danger of the operating fluid being emitted at the exhaust flange if overfilled.
Drain the operating fluid to the normal level before restarting the pump.
CAUTION
Hot surface!
Danger of burns if hot parts are touched. The surface temperature of the pump may
rise above 105 °C in case of malfunction.
Carry out work on the pump only after it has cooled to a safe temperature.