CB 240 Climbing Formwork
Instructions for Assembly and Use – Standard Configuration
B1 Work on the Construction Site
Mounting of the CB 240
Finishing Platform
Preparation
1. Remove tacked on planking parts from
both sides of the platform beam.
2. Attach 4-sling lifting gear to the four
bolts and move finishing platform to
the assembly area. (Fig. B1.24)
Connecting to the Brackets
Connections are done using Bolts
M16 x 130 ISO 4014-8.8, nuts and spring
washer (9.6) (supplied with components).
Initially, only loosely tighten bolts for the
articulated connections.
1. Connect Guardrail Post 200 (9.3) to the
bracket and tighten bolts (9.6). Bolt on
top part of wind bracing (6.2/7.2).
2. Attach platform unit to the Strongback
and lift out of the anchoring. (Fig. B1.25)
3. Pivot platform unit over the finishing
platform.
4. Bolt Platform Post 225 (9.1) to Post
Extension 180 (9.2) and fix at an angle
with bolt (9.6) to the bracket and
finishing platform. (Fig. B1.26)
Depending on the concreting height,
use top or bottom hole, see
Fig B1.28.1 – B1.28.4.
5. Fix the Guardrail Post 190 (9.4) or Gu-
ardrail Post 370 (9.5) to Guardrail Post
200 (9.3) at an angle using bolt (9.6).
Depending on the concreting height,
use top or bottom hole, see
Fig. B1.28.1 – B1.28.4. Mount wind
bracing (6.3/7.3).
6. Fix the toe board at the lower end.
(Fig. B1.27)
Fig. B1.25
Fig. B1.26
Fig. B1.27
9.6
Fig. B1.24
9.6
9.3
6.2/7.2
9.6
9.6
9.1/9.2
9.6
9.6
9.4/9.5
6.3/7.3
9.6
9.3
9.6