This chapter describes the basic steps for validation and diagnosis of a
FOUNDATION Fieldbus or PROFIBUS PA segment during installation
and commissioning. For further information about possible topologies
and more detailed installation information please refer to the FOUNDA-
TION Fieldbus System Engineering Guidelines (AG-181) or the Pep-
perl+Fuchs „Wiring and Installation Guide for FOUNDATION Fieldbus“.
Initial Cable Checkout
Requirements
•
Cables and junction boxes are installed
•
No power supplies and field devices are connected to the seg-
ment
Possible Measurements/Checkouts
Using an external LCD meter or a Checkbox, you can measure:
•
Connection between signal lines and cable shield
•
missing Terminator
•
exceeded cable capacity
•
cable shields not connected to ground
Segment Checkout
Requirements
•
Cables,
•
Power Hub,
•
HD2-DM-A and
•
supply power
are connected to the segment.
Possible Measurements/Checkouts
•
Type of motherboard
•
Motherboard redundancy
•
Primary and secondary supply power
•
Type of Power Module (Power Supply/Power Conditioner)
•
Correct Power Module configuration/combination
•
Correct function of the power supplies
•
Segment supply power
•
Segment current consumption
•
DC Segment unbalance
Network/Communication Checkout