- 5 -
Section 3.0 – DRYER INSTALLATION
NEVER work on unit under pressure
NEVER work on unit when power is connected.
DO NOT over pressurize unit.
DO NOT pass air through the unit until it has been stabilized (operating 2 - 15 minutes).
The larger the dryer, the longer it takes to stabilize. Let unit cycle 2 – 3 times to stabilize.
Plumbing the Air Lines
The dryers are shipped ready to run. All connections are made to the outside of the cabinet.
Air piping
must be
supported independently of the dryer.
Direction of the air flow must be observed for proper installation. (Fig. 1)
General Layout
For Connections
(all connections are labeled)
H
2
0 In/Out
(if water cooled)
Drain
Use unions or flange joints on inlet and outlet pipe connections. (Fig. 2)
If vibration is present, flexible metal hoses must be installed to prevent the vibration
from being
transmitted to the dryer.
Install a bypass line and gate valve to permit isolation of the dryer from the air system. This is
done to provide easy service and/or removal of the dryer without interruption of air to the system.
CAUTION
!
Fig. 1
Summary of Contents for Airtek SMART CYCLE PLUS 100
Page 6: ...6 Fig 2 Models 80 300...
Page 26: ...26 Section 8 0 MAINTENANCE CHARTS cont Element Replacement Log Part No Date Initials...
Page 27: ...27 Section 9 0 ASSOCIATED DRAWINGS...
Page 28: ...28...
Page 29: ...29...
Page 30: ...30...
Page 31: ...31...
Page 32: ...32...
Page 33: ...33...
Page 34: ...34...
Page 35: ...35...
Page 36: ...36...
Page 37: ...37...
Page 38: ...38...
Page 39: ...39...
Page 40: ...40...
Page 41: ...41...
Page 42: ...42...
Page 43: ...43...
Page 44: ...44...