BSP-MT
1-8/D3
Start-up
◊
Carry out all prescribed tests and checks.
◊
Before start-up, ensure that no tools or other foreign parts have been left lying in a part of
the dryer where they might pose a hazard to the dryer being started up.
Requirements for initial start-up
For the fi rst start-up the following preconditions must have been met:
◊
The pipe system is free from contaminations.
◊
All shutdown valves are closed.
◊
The dryer is correctly sited and installed.
Checks before start-up
Ensure that
◊
all pipe, cable and bolt connections on the dryer have been retightened,
◊
no pipes chafe against body edges,
◊
all mountings are perfectly secure,
◊
the needle valve of the oil indicator is closed,
◊
the electrical connections are in safe contact and in good condition,
◊
owner-end and pressurised parts such as safety valves or other devices are not blocked up
by dirt or paint,
◊
all compressed air system parts which are pressurised (valves, hoses etc.) are free from
wear symptoms and defects.
Setting times of the operating phases
In its standard version the dryer is delivered with a time-dependent control system. The
phase sequence occurs in a fi xed cycle.
With the optional dewpoint-sensing control, the dryer can also be operated at variable cycles
(depending on the dewpoint).
The following table provides information on the duration of the individual phases
Phase duration
Fixed cycle
Variable cycle
Adsorption
5 min
10 min, max
Regeneration, total
5 min
5 min
- of which: expansion time
~ 0,2 min
~ 0,2 min
- of which: dehumidifi cation time
~ 4 min
~ 4 min
- of which: pressure build-up
~ 1 min
~ 1 min
Standby
--
~ 55 min, max.