EN
| User Manual
Transportation, installation and storage
BSP-MT 1-8/D3
11
Transporting and installing the dryer
Requirements for the installation site
The conditions at the installation site have a large infl uence on the functional capability of the
dryer and the service life of the drying agent. In order to ensure a mode of operation, which is
as continuous as possible, and low maintenance, the installation site must meet the following
requirements:
◊
The installation site must be located within a building. Protect the dryer against moisture.
◊
The ambient temperature must not drop below +1,5 °C (34,7 °F).
◊
Heed the dryer’s noise emission when selecting the installation location.
◊
The installation area must be level, fi rm and vibration-proof. It must have the necessary car-
rying capacity for the weight of the dryer. The weight of the dryer is specifi ed in the technical
data section of the annex.
◊
The dryer should be installed with suffi cient
spacing at the top, sides, and rear, in order to
be able to carry out maintenance work and
change the drying agent without any hindranc-
es (see fi gure).
If in doubt, the installation site must be inspect-
ed by specialists. If you have any queries in this
regard, please contact the manufacturer (see
pag. 4
D
1 m
D
1 m
1 m
D
1 m
D
D
1 m
Necessary spacing at the top and sides
= min. 1 m
Transporting and installing the dryer
Warning against damage to property!
The dryer is delivered standing on its side on a transportation pallet. Top and
sides have not been designed for mechanical loads. Therefore do not place any
load onto the top face. Do not stack.
Therefore, always transport the dryer on a lifting or forklift truck.
The dryer should only be transported in an upright position.
Note the weight of the dryer!
Depending on its size, the dryer may weigh up to approx. 110 kg. Take this into
account with regard to the following work steps!