8. Machine Installation
25 |
P a g e
8. Machine Installation
Expert M.S.K. personnel will carry out all procedures with regard to loading and unloading and
conduct performance tests for assembly, mounting and start-up, if necessary. These procedures
are evaluated on machine basis and carried out for products deemed necessary. Setting up of
parts and equipment which should be prepared prior to machine use must be performed.
Required operations will be explained below.
8.1. Machine Placement
Use predefined hanger lifting points to position the machine at the site described in the plant
layout. You may adopt previously exemplified transport methods. Using any other method may
damage your machine.
8.2 Fixing on Ground
The machine must be placed considering the maintenance and operating spaces. Rear and side
spaces and spaces recommended for maintenance procedures are above-mentioned. An
expansion bolt at a size of M12X50 mm is recommended for floor connection.
8.3 Start-up Preparation
Moving parts of the machine are generally cleaned by an anti-rust oil. Power connection and
pneumatic connection are made for the machine to function properly.
8.4 Electrical Connections
VOLT
400 V
HERTZ
50 Hz
CURRENT
2.4 A
POLE
3P+N+E
Summary of Contents for OMRM 121
Page 10: ...3 Machine Description 10 P a g e...
Page 14: ...4 Machine Layout and Unit Structure 14 P a g e 4 1 General Machine Size 1137 700 1182 490...
Page 20: ...6 Safety Equipment 20 P a g e...
Page 38: ...9 Machine Use 38 P a g e Loosen the fixing screw with a wrench Remove the clamping springs...
Page 51: ...13 Annexes 51 P a g e...
Page 52: ...13 Annexes 52 P a g e...
Page 53: ...13 Annexes 53 P a g e...
Page 54: ...13 Annexes 54 P a g e...
Page 55: ...13 Annexes 55 P a g e...
Page 56: ...13 Annexes 56 P a g e...
Page 57: ...13 Annexes 57 P a g e...
Page 58: ...13 Annexes 58 P a g e...
Page 59: ...13 Annexes 59 P a g e...
Page 60: ...13 Annexes 60 P a g e...
Page 61: ...13 Annexes 61 P a g e...