VZR.235900.000 IG
Cube С-04 Turnstile
Installation Guidelines
23
Figure 11 - LEDs are installed in the mainboard to check its operation.
1)
D5 indicates the command issued to “LEFT” input.
2)
D6 indicates the command issued to “RIGHT” input.
3)
D7 indicates the command issued to “STOP” input.
4)
D10 indicates the right passage performed and the relay actuation (Ok1 – right).
5)
D16 indicates the left passage performed and the relay actuation (Ok2 – left).
6)
D15 indicates the 12V power supplied to the mainboard
7)
D12 EncDec and D13 EncInc indicate the correctness of magnet location in relation
to the magnetic position sensor of barrier arms. When in correct location, D12 and
D13 are not illuminated.
5.4 Connecting control panel to AMCS controller
In some cases, the RC panel of the turnstile shall be connected directly to
AMCS controller as the passages authorized from the panel (without controller
participation), are perceived by the system as “hacking”.
For using this scheme, set the jumper on the mainboard (Figure 11 -
Х3) to
the “On” position.
With the set
jumper Х3, the turnstile does not respond to panel’s commands,
but only transmits their status to the contacts of the motherboard terminal blocks
(Figure 10 - OUT1...OUT3), which are the outputs with open collector.
Purpose of contacts is given in Table 4, Figure 12 - numbering of panel’s
buttons. For this group of contacts, the maximum output current is 150 mA max,
permissible voltage is 24V max.