Biotube ProPak and LOS Pump Package Installation Manual

Step 2. Install Tank Adapters and Risers, cont.

 

Key Points:

•  Watertight seams and penetrations are critical for proper performance.
•  Before installing the risers, make sure that: 

– All risers are the correct height. Recommended riser height is  
  2in (50mm) above final grade. 
– All risers are being installed in their correct locations. 
– All penetrations are at the correct height for the connections. 
– All penetrations are aligned correctly for good pump package access. 

•  After installing the risers, make sure that: 

– All adhesive seams are free of voids, with smooth, continuous fillets. 
– The adhesive is set before backfilling or testing watertightness.

Step 3. Test Tank and Adapter Seams for Watertightness

Test the tank and the tank-to-riser seams for watertightness. Follow the 
manufacturer’s instructions.

•  Some manufacturers require a partial or full backfill around the tank 

before testing watertightness. 

•  Use NIN-RLA-RR-1, 

PVC Access Riser Installation Instructions

 to test the 

seams between the access riser, tank adapter, and tank for watertightness.

Key Points:

•  Plug the tank’s inlet and outlet before testing watertightness. 
•  Fill the tank with water to a level 2in (50mm) into the riser. 
•  All seams between the tank and access riser must pass the watertightness 

test before you continue. 

•  Follow all applicable regulations for watertightness testing. 

Step 4. Install Biotube Pump Package

Install the pumping components from a Biotube pump package into the 
interceptor/septic tank. 

Step 4a:

 Install a Biotube pump vault and Biotube effluent filter. 

•  For Biotube pump vaults, see NIN-PVU-1, 

Biotube Pump Vault Installation 

Instructions

.

•  For PVP-series Biotube pump vaults, see NIN-PVU-3, 

PVP-Series Biotube 

Pump Vault Installation Instructions

.

Key Point: 

Pump vault placement and orientation is important – it 

affects the location of the pump, discharge assembly, and splice box. 

Fill the tank to a 
level 2in (50mm) 
into the riser.

Access riser

Access riser

2in  

(50mm)

Test seams for watertightness.

Test seams for watertightness.

3

Orenco pump vault types (from NIN-PVU-1, 

Orenco pump vault types (from NIN-PVU-1, 

Biotube Pump 

Biotube Pump 

Vault Installation Instructions

Vault Installation Instructions

).

).

4a

PV and “Standard” PVU

“Earless” PVU

Support 

pipes

Installation Steps

Summary of Contents for Biotube ProPak

Page 1: ...Installation Manual 1800348 9843 15414594449 www orenco com Biotube ProPak LOS Pump Package Installation Manual 1 800 348 9843 1 541 459 4449 www orenco com...

Page 2: ...products come with installation instructions and all of these instructions are available in hardcopy form Contact your distributor or Orenco for copies or find instructions online in the Orenco Docume...

Page 3: ...which is available from your local distributor from Orenco and online at www orenco com products Note All pipe diameters given are US nominal IPS pipe sizes If you re using metric pipe you may need a...

Page 4: ...grades are met Step 2 Install Tank Adapters and Risers Step 2a Install the tank adapters if they haven t been installed Follow the manufacturer s instructions For Orenco PRTA24 or PRTA30 Tank Adapter...

Page 5: ...tions to test the seams between the access riser tank adapter and tank for watertightness Key Points Plug the tank s inlet and outlet before testing watertightness Fill the tank with water to a level...

Page 6: ...y Installation Instructions NIN MF DA 1 Float Switch Settings and Adjustments Instructions IMPORTANT DON T change the float tether lengths Step 5 Connect Pump Discharge to Transport Service Line Glue...

Page 7: ...a Open the discharge plumbing valve and service connections Step 7b Unsnap the float switch assembly and remove it from the riser If the assembly includes a Redundant Off Low Level Alarm float switch...

Page 8: ...larm switch in the down position The audible alarm goes silent the panel door alarm light turns off Place the Pump On Off switch in the down position The pump stops running Place the Redundant Off Low...

Page 9: ...the panel door alarm light turns on Timed Dose Y R W or YG R W Float Switch Assemblies MVP S Control Panels Go to the logo unit s input screen per the instructions supplied in the panel Place the Red...

Page 10: ...iser Make sure the coils don t tangle with the float switches Step 8e Place the Auto Off Man switch on the control panel to Auto make sure the control panel circuit breakers are in the On position and...

Page 11: ...Orenco Systems 800 348 9843 1 541 459 4449 www orenco com NIM EPS 1 Rev 6 10 21 Page 11 Biotube ProPak and LOS Pump Package Installation Manual...

Page 12: ...1 800 348 9843 1 541 459 4449 www orenco com NIM EPS 1 Rev 6 10 21 Orenco Systems Installation Manual Biotube ProPak LOS Pump Package...

Reviews: