Step 5:  Excavate and Set AX20-RT Unit   

Before installing the AX20-RT, consider the depth of the septic 

tank and the height of the septic tank outlet. Remember that there 

must be a minimum 

1

8

 in. per foot slope (10 mm per meter or 1%) 

from the outlet of the septic tank to the inlet of the AX20-RT, if 

the septic tank uses a gravity discharge. Also, remember that the  

AX20-RT lid needs to sit 2 in. (50 mm) above finished grade, to 

allow for settling and drainage. Take into account any planned 

landscaping that might affect the finished grade of the system.

NOTE: 

If you are installing counterbuoyancy flanges, com-

plete step 6a before setting the AX20-RT unit.

Step 5a: 

Mark the outline of the excavation. The excavation 

needs to extend 18-24 inches beyond all four sides of the unit.

Step 5b: 

Excavate the hole for the unit. The AX20-RT unit height  

is 72 in. (1830 mm). Make sure that the unit will be set deep 

enough to facilitate a minimum slope of 

1

8

 in. per foot (10 mm per 

meter or 1%) from the septic tank if the septic tank uses a gravity 

discharge. Also make sure that the lid will be 2 in. (50 mm) above 

final grade after the hole for the unit is excavated and after a com-

pacted bed of aggregate or pea gravel — if necessary — is laid. 

Step 5c: 

Make sure the bottom of the excavation is stable and 

free of debris, especially rocks and other sharp objects. 

  •  If 

the base soil is unstable (peat, quicksand, muck, soft or  

    highly expansive clay, etc.), overexcavate the site depth and  

    then set a firm, 6-in. (152-mm) compacted base of ½-in.- to  

    ¾-in.-minus (13- to 19-mm) aggregate or pea gravel. In ex- 

    tremely unstable soil, a concrete layer may be needed to stabi- 

    lize the bottom of the excavation. If you have any doubt about  

    the soil’s ability to support the tank,consult a local civil or  

    structural engineer.

  •  If 

the base soil is rocky or uneven, lay a 4-in. (100 mm) bed  

    of sand or pea gravel less than 

3

8

 in. (10 mm) in diameter, and  

    compact the material to create an even, smooth surface. 

Step 5d: 

Use properly sized lifting equipment to attach a chain or 

cable to the two lifting brackets on the top of the AX20-RT unit. 

Carefully lift and lower the unit into the excavation. When the unit 

is set and level in the correct position, remove the chain/cable.

WARNING: Do not allow workers to stand in or near the  

excavation while placing the unit!

 

CAUTION: 

Use a lifting device that will not damage the unit 

or the lid of the unit.

2 in. (50 mm)

5a

5b

62 in. 

(1.57 m)

102 in. 

(2.6 m)

5d

5d

Excavate 18-24 in. (457-610 mm) beyond all four sides of 

the unit.

Excavate so that the lid sits at 2 in. (50 mm) above final grade.

Summary of Contents for AdvanTex AX20-RT

Page 1: ...AdvanTex AX20 RT Treatment Systems An illustrated guide to installing an Orenco AdvanTex AX20 RT Treatment System 800 348 9843 541 459 4449 www orenco com www vericomm net Orenco Systems Incorporated...

Page 2: ...ew before shipping If this system or any of its components possesses flaws that would inhibit its proper func tioning please contact your authorized AdvanTex Dealer The Dealer can also provide repair...

Page 3: ...sting primary tank must have an at grade access with a securable and removable lid If it doesn t an at grade access must be installed onto the primary tank and be made watertight The primary tank must...

Page 4: ...ayer passes through a Biotube effluent filter and is discharged by gravity to the recirculating treatment tank portion of the AX20 RT unit which contains a Biotube Pump Package The Biotube Pump Packag...

Page 5: ...ans or with plans of limited detail contact your local Dealer or Orenco for design assistance Determine and sketch the exact positions of the primary tank and AX20 RT unit on the site Account for curr...

Page 6: ...emember that you need the correct depth for a consistent slope of 1 8 in per foot 10 mm per meter or 1 from the septic tank outlet to the inlet of the AX20 RT Step 2c Make sure the bottom of the excav...

Page 7: ...m into the riser because structural damage to the tank may occur The inlet and outlet pipe into the tank needs to be turned up or plugged to allow the tank to be filled CAUTION Check the tank manufact...

Page 8: ...the unit is excavated and after a com pacted bed of aggregate or pea gravel if necessary is laid Step 5c Make sure the bottom of the excavation is stable and free of debris especially rocks and other...

Page 9: ...Apply a in 19 mm bead of SS115 or SS140 adhesive down the length of each flange 4 Slide the flanges under the AX20 RT unit and then lower the unit onto the flanges Allow the adhesive to set before mo...

Page 10: ...ill to minimize settlement and provide sup port for the walls of the unit Step 7c After the first layer of backfill is complete fill the tank with water to just above the midseam flange on both sides...

Page 11: ...AX20 RT unit Be sure the vent line is sloped to drain towards the unit and that the passive air vent is within 20 ft 6 m of the unit After installation the top of the passive air vent should be a mini...

Page 12: ...nclude the following items a Incoming power to the panel One or more circuits may be required depending upon the number of pumps and local electrical codes b Incoming phone line to the panel for VeriC...

Page 13: ...isabled Local audible and visual alarms are activated as alarm conditions occur System Data Logs are suspended and Timer cycles are shortened Step 10f Familiarize yourself with the floats on the syste...

Page 14: ...Comm Monitoring System A red LED Modem Activity component should illuminate indicat ing that the controller has established communication with the host This may take a few minutes Once the communicati...

Page 15: ...desired squirt height is not achieved or the unit does not pressurize check for debris breaks or closed valves Also verify that the pump is receiving sufficient power If the unit still does not pressu...

Page 16: ...non cohesive soils with high seasonal water tables use in crushed rock as the backfill material The top of the AX20 RT lid should sit 2 in 50 mm above final grade IMPORTANT After backfilling call the...

Page 17: ...Installation Manual AdvanTex AX20 RT Treatment Units NIM ATX AXRT 1 Rev 1 0 1 10 2010 Orenco Systems Inc 16 Notes 17...

Page 18: ...Installation Manual AdvanTex AX20 RT Treatment Units NIM ATX AXRT 1 Rev 1 0 1 10 2010 Orenco Systems Inc Notes 17...