Connect a Terminal or Emulator to the SER MGT Port
Caution -
Do not attach power cables to the power supplies until you have connected the server
to a serial terminal or a terminal emulator (PC or workstation). The server goes into Standby
mode and the Oracle ILOM SP initializes as soon as a power cable connects a power supply
to an external power source. System messages might be lost after 60 seconds if a terminal or
terminal emulator is not connected to the SER MGT port before power is applied.
Note -
Oracle ILOM will signal a fault if all four power supplies are not cabled at the same
time, since it will be a nonredundant condition. Do not be concerned with this fault in this
situation.
Route the power cords from the AC power source to the rear of the server.
Do not attach the power cords to the power supplies at this time.
Related Information
■
“Rear Panel Components” on page 15
■
“Power on the Server for the First Time” on page 68
Connect a Terminal or Emulator to the SER MGT Port
Prior to powering on the server for the first time, make a serial connection to the SP from a
terminal or terminal emulator. After making this serial connection, you will be able to view the
system messages when you connect the power cords.
1.
Confirm that you have completed the following tasks:
a.
Completed the preparation for installation.
See
“Preparing for Installation” on page 23
.
b.
Completed the installation of the server in a rack.
See
“Installing the Server” on page 29
c.
Connected the necessary cables.
See
“Connecting Cables” on page 51
2.
Connect a terminal or a terminal emulator (PC or workstation) to the server SER
MGT port.
66
SPARC T7-4 Server Installation Guide • March 2017
Summary of Contents for SPARC T7-4
Page 1: ...SPARC T7 4 Server Installation Guide Part No E54993 04 March 2017 ...
Page 2: ......
Page 8: ...8 SPARC T7 4 Server Installation Guide March 2017 ...
Page 10: ...10 SPARC T7 4 Server Installation Guide March 2017 ...
Page 22: ...22 SPARC T7 4 Server Installation Guide March 2017 ...
Page 28: ...28 SPARC T7 4 Server Installation Guide March 2017 ...
Page 64: ...64 SPARC T7 4 Server Installation Guide March 2017 ...
Page 86: ...86 SPARC T7 4 Server Installation Guide March 2017 ...