11.
Gently tug on the four CMA connection points to ensure that the CMA connectors are
fully seated before you allow the CMA to hang by its own weight.
12.
Install and route cables to the controller, as required.
Verifying Operation of the Oracle ZFS Storage ZS7-2 Slide-Rails
and CMA
Use the following procedure to verify the operation of the cable management arm (CMA) and
slide rails for an Oracle ZFS Storage ZS7-2 controller.
Before You Begin
Ensure all rack anti-tilt devices are extended to prevent the rack from tipping forward when
the storage controller is extended from the rack.
1.
Slowly pull the storage controller out of the rack until the slide-rails reach their stops.
2.
Inspect the attached cables for any binding or kinks.
3.
Verify that the CMA extends fully with the slide-rails.
4.
Push the storage controller back into the rack and verify that the CMA retracts without
binding.
5.
Adjust the cable straps and the CMA, as required.
Chapter 5
Verifying Operation of the Oracle ZFS Storage ZS7-2 Slide-Rails and CMA
5-11