28
Ready to Start
Check List
Before starting the system, check following items:
Item
Point of check
Checked?
Mounting
•
SP5000 Vitality Eco is firmly
mounted on the bracket
•
Bracket is firmly fixed
AC
•
All wires are firmly fixed on
terminals
•
All polarities are correct
•
Protective Ground is available
and connected
PV
•
All wires are firmly fixed on
connectors
•
Polarities are correct
•
PV open voltage (V
PV, OPEN
) is less
than maximum voltage of PV
input
•
Internal and/or external DC
switch are on before operation
RS485
•
Wires and cables are locked and
fixed
•
Polarities are correct
•
For multiple units, be sure to set
their RS485 in different
addresses
DC (Battery)
•
All cables are firmly secured
•
Polarity is correct
•
Breaker/Fuse is on
•
Battery sensor is installed and
connected
CANbus cables
•
All cables are firmly secured
•
Polarity is correct
•
Check DIP switch 2 positions
•
The wire lengths of different
inverters should be the same
Summary of Contents for SP5000 Vitality Eco
Page 1: ...Installation Operation Manual SP5000 Vitality Eco...
Page 2: ...This page is intended to be blank...
Page 7: ...5...
Page 18: ...16 Keep distance for the airflow to dissipate heat Mounting Procedure 1 2 3...
Page 24: ...22 Battery sensor Accessory F Protection cover Protection cover From BAT breaker...
Page 29: ...27...
Page 31: ...29 Start up Procedure...
Page 57: ......