Outdoor Living Today www.outdoorlivingtoday.com [email protected]
Page 23
34.
At the peak, align Ridge Boards so they are flush together and secure
them with
12 - 1 1/4” Screws.
To completely secure Ridge Boards, place
4 - 3/4” Screws
into any of the remaining Metal Ridge Board Connector
holes. Complete both sides.
Important:
If there is a gap between Ridge
Boards, try pushing side walls closer together from outside. Walls should be
91” apart at top from inside of wall plate to wall plate.
Hardware
1 1/4” Screws
x 12 total
3/4” Screws
x 8 total
Offset Metal Ridge
Board Connectors
Important:
If gable framing does not line up with Rafters, remove temporary 2” Screws from Gable
framing. Re-align gable and secure with 8 - 2” Screws total.
35.
With both Ridge Boards connected, completely secure Rafters to Gable
framing of both Gable Walls. Use
8 - 2” Screws
per gable. Use another
6 -
2” Screws
to attach Gable Walls to Side Wall framing. Complete both sides.
Hardware
2” Screws
x 28 total