INSTALLATION | Preparing to install the appliance
982000-AIR-M2-M4-EN03.1 | www.ochsner.com 15
»
Ensure that the outdoor unit is adequately secured,
paying regard to the wind load occurring at the instal-
lation location.
CAUTION: Risk of slipping
If drainage for condensation is inadequate, ice can
build up in winter in the area around the outdoor
unit.
»
Ensure drainage for condensation is sufficient
even at low temperatures.
i
Information
Insulation used beneath the soil must be made of
a closed-cell material. Otherwise, the thermal in-
sulation of the material will be impaired.
9.3.1 Laying spot foundations
11_04_200_504_001
900
B
Ø250
A
C
4
2
1
3
1 Pipe liner for the connecting lines (where installed
underground)
2 Gravel bed
3 Drainage pipe (frostproof)
4 Spot foundation (with underground waste pipe)
A
B
C
AIR 7
1110
270
≥ Ø160
AIR 11
1110
270
≥ Ø160
AIR 18
1110
270
≥ Ø160
AIR 23
2040
300
≥ Ø200
AIR 29
2040
300
≥ Ø200
AIR 41
2040
330
≥ Ø250
Use underground waste pipes when installing spot foun-
dations. When installing spot foundations, we recommend
the following approach:
11_04_200_504_003
≥ 800
900
100
»
Dig out the foundation trench.
»
Place in position four underground waste pipes
(Ø ≥ 250 mm).
»
Ensure correct horizontal and vertical positioning of
the underground waste pipes.
»
Place a drainage pipe along the base of the trench.
11_04_200_504_004
≥ 1800
1
2
3
4
1 Underground waste pipe
2 Pipe liner for underground connecting lines
3 Drainage pipe (frostproof)
4 Gravel bed
»
In the case of underground connecting lines, allow for
the pipe liner.
»
Fill the foundation trench with coarse gravel. If the
pipe liner (with refrigerant lines) is to be installed at
a later point, in the case of underground connec-
tion lines, this must be allowed for in the foundation
trench.
»
Fill the underground waste pipes with concrete.