©Novinium, Inc. 2016, all rights reserved.
NRI 603 – Small Diameter Cables – SPR
Revised: February 19, 2016
Page
11
of
11
Recording Tank Levels
1.
Record the injection end time and feed tank level.
Record the feed tank’s ending fluid level in
millimeters
(mm) from the sight gauge.
Record the time the injection ended.
Enter this information into Knomentous.
2.
Remove the injection equipment.
Close all valves on the injection assembly and turn off the CO2 supply.
Vent all pressure from the tanks if they will be moved or stored for the night.
Open the valve on the feed tank’s injection port to vent pressure and fluid from the liquid flow meter
back into the feed tank.
3.
Attach Craft Tags
The Novinium certified craftsman must attach their craft tag onto each IA or component body. Secure the
tag with tape to ensure it will not move.
Figure 18:
Craft tag placed over the IA.
Figure 19:
Craft tag placed on the component.
The SPR injection process is complete.
Resuming Component Installation
SPR injection interrupts the component installation. Resume installation using the associated NRI.
Attach warranty tags.
Enter data into Knomentous.