Diagram #5
CASING INSTALLATION PROCEDURE
INSTALLATION PROCEDURE
1.
Place 30 x 110 piece of insulation over top of boiler and down sides.
2.
Place bottom rear panel (1) in place with inlets through holes in panel. Rear extension (8) is placed below (1). (1) and (8) may
be shipped in one piece.
3.
Place top rear panel (2) above stack box.
4.
Fasten side panel extensions (9) to bottom of side panels (3) and (4).
5.
Place side panel (3) against boiler, and over the ends of panels (1), (2) and (8). Insert 1 screw to hold panels (2) & (3), 2
screws to hold panels (1) & (3) & 2 screws to hold panels (8) & (9).
6.
Repeat step 4 with side panel (4).
7.
Fasten top front panel (5) above access doors to panel (3) with 1 screw and to panel (4) with 1 screw.
8.
Fasten bottom front panel (6) below fire door with 2 screws into panel (3) and 2 screws into panel (4).
9.
Place top panel (7) over top of other panels and fasten in place with screws.
ITEM
DESCRIPTION
PART NUMBER
QUANTITY
1 & 8
Bottom Rear Panel
4150038
1
2
Rear Panel Liner Top
4150037
1
3
Right Side Panel
4150029
1
4
Left Side Panel
4150030
1
5
Top Front Panel
4150032
1
6A
Bottom Front Panel
4150036
1
6B
Bottom Front Panel c/w
Secondary Air Openings
4100134
1
7
Top Panel
4150031
1
9
Side Panel Extension
4150033
2
Summary of Contents for BC 160
Page 21: ...20 DIAGRAM 4 SECONDARY AIR OPENINGS LOW WATER CUT OFF FITTING...
Page 23: ...22 DIAGRAM 6 GENERAL ASSEMBLY...
Page 24: ...23 Diagram 7 FLUE PIPE CONNECTION Diagram 8 MINIMUM INSTALLATION CLEARANCES...
Page 25: ...24 Diagram 9 CONTROL PANEL...
Page 26: ...25 Diagram 10A FIELD WIRING...
Page 27: ...26 Diagram 10B FIELD WIRING WITH LOW WATER CUT OFF...
Page 28: ...27 Diagram 11...
Page 29: ...28 Diagram 13A...
Page 30: ...29 Diagram 13B...
Page 31: ...30 Diagram 14 WOOD ADD ON WIRING...
Page 32: ...31 Diagram 15A...
Page 33: ...32 Diagram 15B...
Page 34: ...33 Diagram 16A TYPICAL PIPING ZONING WITH CIRCULATORS...
Page 35: ...34 Diagram 16B TYPICAL PIPING ZONING WITH ZONE VALVES...
Page 36: ...35 Diagram 17 Diagram 18...
Page 37: ...36 Diagram 19 Diagram 20...
Page 38: ...37 Diagram 21 SHAKER GRATE INSTALLATION PROCEDURE...
Page 39: ...38 Diagram 22 GRATE INSTALLATION PROCEDURE Diagram 23 CASTING INSTALLATION...
Page 41: ...40 Diagram 24 SECONDARY AIR SYSTEM GENERAL ASSEMBLY...
Page 42: ...41 Diagram 25 SECONDARY AIR SYSTEM INSTALLATION...