Continuous production monitoring
In continuous production monitoring, visual inspection of all welded studs is typically sufficient. On suspicion of
a faulty weld, a bending test or a tension test must be carried out.
If the requirements are not met, a bending or tension test must be carried out on the 2 previous welds and on
the 3 subsequent welds. The test results must be recorded in the production log.
It must be noted that the welding work may only be continued when the test
results are satisfactory.
5.7.1 Short Cycle Method - Visual Inspection
Inspection and testing of the weld is restricted in this manual to the visual inspection of welds. A description of
the mechanical and technological tests involved would go beyond the scope of the manual.
+
See EN ISO 14555
2
for detailed information in this regard.
2
EN ISO 14555: Welding Arc stud welding of metallic materials (2006)
Perfect weld.
Even bead, no
perceptible errors.
Corrective measures:
Not necessary. No alteration
to the electrical and mechanical parameters.
Faulty weld #1.
Cross section
not fully welded.
Corrective measures:
Increase weld current and/or
time, possibly change polarity.
Faulty weld #2.
Large, uneven
bead.
Corrective measures:
Reduce weld time.
Faulty weld #3.
Pores in bead.
Corrective measures:
Reduce weld time or
increase weld current, weld in shielding gas.
Summary of Contents for ArcCharger N550C DOMESTIC
Page 18: ...Part No 729 110 040 Rev 1 41 June 2016 2016 Nelson Stud Welding Inc All Rights Reserved 17 ...
Page 60: ...Part No 729 110 040 Rev 1 41 June 2016 2016 Nelson Stud Welding Inc All Rights Reserved 59 ...
Page 62: ...Part No 729 110 040 Rev 1 41 June 2016 2016 Nelson Stud Welding Inc All Rights Reserved 61 ...
Page 64: ...Part No 729 110 040 Rev 1 41 June 2016 2016 Nelson Stud Welding Inc All Rights Reserved 63 ...