3.7.3
Cable Termination and Cross Connection from the DRU-30-A/DRU-30-S3 to the Analog PB TEL/
D
term
Figure 3-26 Connection of Analog PB TEL/D
term
START
Cable running
Termination of Cables
Check terminal locations on the
DRU-30-A/DRU-30-S3 side of the
IDF
Cross Connection
END
While referring to Figure 3-26, run cables between each Analog
PB TEL/D
term
and its Modular Block (Jack), and between the
Modular Blocks and the IDF.
Protect the cables using cable ducts, etc.
While referring to Figures 3-27 and 3-28, terminate the installed
cables to the IDF and the Modular Blocks.
While referring to Figure 3-29, identify the lead names for the
CHAMP Connector of DRU-30-A/DRU-30-S3 and the termi-
nal locations of the leads.
While referring to Figures 3-27 and 3-28, provide cross connec-
tions at the Analog PB TEL/D
term
side and the DRU-30-A/
DRU-30-S3 side.
DRU-30-A/DRU-30-S3
IDF
MODULAR BLOCK
(JACK)
CHAMP
CONNECTOR
(MALE)
CHAMP Connector Cable (25P)
1-PAIR CABLE
MODULAR
CABLE
CHAMP0
CHAMP1
DRE card
Analog PB TEL
or D