Using the EISA Configuration Utility
5-14
Using the System Utilities
Adding or Removing Boards
Each time you add or remove a board, you must reconfigure your server using
the EISA Configuration Utility program.
Adding Boards
Note: If you are adding a PCI device or a plug-and-play ISA board, proceed
to step 5.
PCI devices and plug-and-play (PnP) ISA boards do not require a
corresponding CFG file. The configuration information is already stored on
the board.
To add a board, follow these steps:
1. Select “Maintain system configuration diskette” from the main menu and
press Enter.
2. From the screen that displays, select “Copy/Update CFG files” and press
Enter. A list of CFG files from your system configuration diskette
displays.
Note: The EISA Configuration Utility uses the CFG file to configure the
board into the system without creating conflict with other boards or
devices.
3. Select the appropriate CFG files and press Enter to return to the
“Maintain system configuration diskette” screen.
4. Select “Return to the main menu” and press Enter.
5. From the main menu, select “Configure computer” and press Enter. The
screen “Steps in configuring your computer” displays.
Summary of Contents for S26
Page 1: ...BST0 2140 4700 12 97 NCR S26 Hot Plug Server User Guide Release 3...
Page 11: ...NCR S26 Hot Plug Server User Guide 1 1 Chapter 1 Installation and Documentation Overview...
Page 19: ...NCR S26 Hot Plug Server User Guide 2 1 Chapter 2 Using System Features...
Page 33: ...NCR S26 Hot Plug Server User Guide 3 1 Chapter 3 Adding and Replacing Components...
Page 52: ...Installing Drives 3 20 Adding and Replacing Components Figure 3 10 Securing the Drive...
Page 56: ...Installing Drives 3 24 Adding and Replacing Components...
Page 57: ...NCR S26 Hot Plug Server User Guide 4 1 Chapter 4 Using the BIOS Setup Utility...
Page 91: ...NCR S26 Hot Plug Server User Guide 5 1 Chapter 5 Using the System Utilities...
Page 109: ...NCR S26 Hot Plug Server User Guide A 1 Appendix A 420 Watt Power Supply Requirements...
Page 112: ...Output Requirements A 4 420 Watt Power Supply Requirements...
Page 113: ...NCR S26 Hot Plug Server User Guide B 1 Appendix B Error Messages...
Page 119: ...NCR S26 Hot Plug Server User Guide C 1 Appendix C Sample Configurations...
Page 141: ...NCR S26 Hot Plug Server User Guide D 1 Appendix D Hot Plug Backplane...
Page 161: ...NCR S26 Hot Plug Server User Guide E 1 Appendix E System Support Log...
Page 188: ...Software Records E 28 System Support Log This page intentionally left blank...
Page 219: ...Index NCR S26 Hot Plug Server User Guide Index 3 V Ventilation 2 7...
Page 220: ...Index Index 4 NCR S26 Hot Plug Server User Guide...