36
7350-K978 R6L Upgrade, Narrow Size Core
Routing I/O Box Cables
To route the I/O Box cables in the NCR SelfServ Checkout unit, follow these steps:
1. Install the I/O Box and Power Supply Bracket to the NCR SelfServ Checkout Narrow
Core unit. For more information, refer to
Installing the I/O Box and Power Supply
2. Using cable ties, wrap the cables and then tie them on corresponding lance bridges
to fix the cables on the mounting plate as shown in the image below.
3. Using cable ties, group the cables exiting to the back of the unit as shown in the
image above.
4. Do any of the following:
•
Install other R6 Lite components. For more information, refer to the
•
Route and sort cables. For more information, refer to
Note:
For more information about routing cables, refer to
SCO R6 Lite (Narrow
Core) Routing Instructions (497-0520486).