Bottom Ac Entry
For bottom entry, ac wiring enters the transmitter cabinet through the floor of the transmitter (see
). Wires must be routed through a pre-planned cable trench in the transmitter room floor.
Wires must fit through a 1.9-inch x 1.9-inch opening in the bottom of the cabinet and a 1-3/8 inch
diameter hole inside the cabinet. For multi-wire conductors, you may need to strip back the cable’s
outer jacket by at least 40 inches to allow individual conductors to pass through the bottom entry holes
(see
) and connect to the power transformer terminals.
Figure 1.5.3: Bottom Ac Entry
BOTTOM AC
CABLE ENTRY
(intended for use when a
cable trench exists beneath the
transmitter)
Portion of rectangular opening
available for cable access:
1.9 in (48 mm) x 1.9 in. (48 mm)
A 1-3/8 in (35 mm) hole exists
above this opening.
Ac wiring must pass through
both access holes
Summary of Contents for NX5 AM
Page 2: ......
Page 4: ......
Page 8: ...NX5 PRE INSTALLATION MANUAL TABLE OF CONTENTS PAGE 1 VIII VERSION 0 1 2015 08 01 ...
Page 10: ...NX5 PRE INSTALLATION MANUAL PAGE 1 X VERSION 0 1 2015 08 01 ...
Page 22: ...NX5 PRE INSTALLATION MANUAL PAGE 1 XXII VERSION 0 1 2015 08 01 ...
Page 79: ...NX5 PRE INSTALLATION MANUAL PARTS AND TOOLS PAGE 1 9 4 VERSION 0 1 2015 08 01 ...
Page 85: ...NX5 PRE INSTALLATION MANUAL PRE INSTALLATION ASSISTANCE PAGE 1 10 6 VERSION 0 1 2015 08 01 ...
Page 88: ......