1.  Introduction 

Overview  of  the  my!Wind  10  kW  turbine  installation  with  a  10  m  self-standing  mast  on  a  foundation 

block is given in this document. The manual is solely intended to be used for a tower corresponding 

with  appendix  01  and  for  a  foundation  corresponding  with  appendix  02.  Please  DO  NOT  attempt  to 

use the manual for any other configuration of my!Wind products or for any products provided by other 

suppliers. This can result in serious harm or loss of life. 

Carefully  read  and  understand  the  disclaimer  at  the  beginning.  While  simple  in  concept,  the 

installation  requires  basic  mechanical  knowledge  and  attention  to  detail.  Tools  listed  to  erect  the 

turbine  are  readily  available  in  most  parts  of  the  world  or  can  be  obtained  from  a  distributor.  When 

even remotely possible use a my!Wind distributor who has received a corresponding training to carry 

out the installation for you.  

2.  Prior to installation 

2.1  Important safety instructions 

1) 

Read, understand and follow all warnings. 

2) 

Install foundation and tower in accordance with the electric code used in  your country or region 

and all local building and zoning codes and requirements. 

3) 

Obtain building and construction permits prior to starting the installation. 

4) 

Make sure that you have enough space for the erection before installing the foundation. 

5) 

Foundation  concrete  must  be  completely  cured  prior  to  installing  tower  (Minimum  20  MPa,  28 

day strength). 

6) 

my!Wind  uses  high  voltage  and  is  potentially  dangerous.  Follow  all  safety  precautions  at  all 

times. 

7) 

Remain  at  a  safe  distance  when  rising  and  lowering  tower.  NEVER  stand  or  walk  under  tower 

while it is being raised or lowered. 

8) 

Be aware of overhead power lines. 

9) 

Do not attempt to raise tower on a windy day (maximum wind speed 5 m/s). 

10)  Always wear personal protection equipment 

– closed toe shoes, work gloves, safety glasses and 

hardhat. 

 

  

Summary of Contents for 10 kW wind turbine

Page 1: ...my WIND Ltd Soola 1a 51013 Tartu Estonia Email info mywind ee Website www mywind ee 1 P a g e 2 6 0 7 2 0 1 9 my Wind Ltd 10 kW wind turbine 10m Tower Installation Manual...

Page 2: ...Placing the tower base plate 9 Step 2 Placing the tower 1 st segment 10 Step 3 Placing the tower 2 nd segment 11 Step 4 Placing the gin pole 12 Step 5 Placing the gin pole cables 13 Step 6 Connecting...

Page 3: ...S 2 45 dual axis inclinometer 25 Annex 2 Tower verticality 26 General remarks Please read this manual thoroughly through before beginning the assembly No guarantee is assumed by my WIND for the correc...

Page 4: ...possible use a my Wind distributor who has received a corresponding training to carry out the installation for you 2 Prior to installation 2 1 Important safety instructions 1 Read understand and foll...

Page 5: ...cables and available open area may require the my Wind to be installed in a less then optimum location In general my Wind will produce more power if installed on a taller tower However towers are expe...

Page 6: ...dation for the tower and turbine Depending on the length of the vehicle and the method used to raise the tower over 18 m might be required on the other side of the foundation for the vehicle lifting c...

Page 7: ...5 Zn Cylinder Head Cap Screw 6 DIN 933 M16 x 40 Zn Hex Head Bolt 16 DIN 933 M20 x 45 Zn Hex Head Bolt 2 DIN 975 M27 x 500 Zn Threaded Bar 6 DIN 127 A 8 Zn Spring Washer 20 DIN 125 A 8 4 A2 Washer 48 D...

Page 8: ...d at least 400 kg 1 11 m rod or 12 m strong blank cable For pushing the wires through the tower 1 Fork lifter tractor crane At least 400 kg of lifting force at least 3000 kg of pulling force 1 Truck w...

Page 9: ...ughly 95 mm from the foundation surface Use WD 40 oil to lubricate the nuts before placing them on the bars 2 Place the tower base plate onto the washers and use a spirit level to level the base plate...

Page 10: ...e you DO NOT place any body part underneath the lifted object while it is being lifted 2 Once the tower segment hinge and base plate hinges are coaxial place the M27 x 500 threaded bar through the hin...

Page 11: ...contact with the tower 2 st segment in order not to damage the zinc layer IMPORTANT Make sure you DO NOT place any body part underneath the lifted object while it is being lifted Make sure that the s...

Page 12: ...RTANT Make sure that the segment is securely supported and shall not fall over Figure 7 Supporting the 2 nd segment Step 4 Placing the gin pole 1 Place the gin pole hinge pipes between tower 1 st segm...

Page 13: ...ment lifting eye pos 1 and the gin pole lower lifting eye pos 2 see Figure 9 and 10 2 Take the 6x19 8 mm cable lifting cable with thimble at one end and a hook at the other end and connect the thimble...

Page 14: ...ip Step 8 Figure 11 Connecting the lifting equipment Step 7 Test lifting the tower 1 Check that all the tower segments are firmly connected together and to the base plate Check that the gin pole is co...

Page 15: ...gment to the tower base plate see Figure 13 Use WD 40 oil to lubricate the bolts before placing them into the threaded holes Fix the bolts cross wise with a torque of 434 Nm going first 50 and then 10...

Page 16: ...upper M27 nuts from the threaded bars this could result in the tower falling down 4 Once the tower is vertically levelled fix the M27 nuts cross wise with a torque of 1080 Nm going first 50 and then 1...

Page 17: ...essure on the lifting cable to prevent the gin pole from falling down 6 Assembling the turbine Step 1 Placing the generator 1 Remove lid and yaw system flange side of the generator transportation box...

Page 18: ...tem flange to tower 2 nd segment top see Figure 16 Use WD 40 oil to lubricate the bolts before placing them into the threaded holes Fix the bolts cross wise with a torque of 222 Nm going first 50 and...

Page 19: ...lts with a spring washer and then a regular A2 washer and place the bolts to join the three blade cover holders to the blade holder back flange see Figure 18 Use WD 40 oil to lubricate the bolts befor...

Page 20: ...53 Nm going first 50 and then 100 TIP Fix at first two bolts with a small torque and then place to others This will make the bolt placement easier 3 Once the blade is fixed place a support under the b...

Page 21: ...cover and place it on top and inside of the cooling ring in a way that the tower passes through the hole for tower see Figure 21 Align the eight fixing holes in the cover and in the cooling ring 2 Ta...

Page 22: ...1 st segment and the base plate HINT Fix the wires with the cable ties to one of the M27 threaded bars 3 Raise the tower slowly carefully observing the tension in the cables If your lifting equipment...

Page 23: ...d bar connecting the gin pole to the tower 1 st segment and remove the gin pole see Figure 8 4 Place the A 28 washers and M27 nuts back onto the M27 threaded bar to be used again for the gin pole if n...

Page 24: ...nd turbine We appreciate your support of our company and products Follow the Electrical connection manual on how to connect the turbine to the controller and after that you are ready to begin harnessi...

Page 25: ...luence of side pressure 5 Take the dual axis inclinometer display and take the reading from the device If the X and Y axis readings on the display are more than 0 5 from the 0 perform next steps of th...

Page 26: ...te from which the turbine is self orienting In this case the turbine blade cover is pointing at the direction which needs to be lifted Use the technique described in Chapter 5 Step 8 to level the towe...

Reviews:

Related manuals for 10 kW wind turbine