LOG PLACEMENT
VDY24/18D4 LOG INSTALLATION SEQUENCE:
1. Place Bottom Front Log (#2) on front of grate.
See Figure
33.
2. Place Back Log (#1) on back of grate lining up two (2) pins
on grate with holes in bottom of log.
See Figures 34 and
35.
3. Place Left Top Log (#3) on left end of Bottom Front and Back
Logs.
See Figure 36.
4. Place Center Crossover Log (#4) across middle of Bottom
Front and Back Logs.
See Figure 37.
5. Place Left Top Crossover Log (#5) up against Left Top Log.
See Figure 38.
6. Rest Right Top Log (#6) on Center Crossover Log and front
of grate.
See Figure 39
Figure 33 - Placing Front Log (#2)
Bottom Front Log (#2)
Figure 37 - Placing Center Log (#4)
Center Crossover
Log (#4)
Figure 38 - Placing Left Top Log (#5)
Left Crossover
Top Log (#5)
Right Top
Log (#6)
Figure 39 - Placing Right Top Log (#6)
Figure 35 - Placing back Log (#1)
Back Log (#1)
Figure 36 - Placing Left Top Log (#3)
Top Left Log (#3)
Figure 34 - base
Locator Pins