4.1.3.1 Load shedding or sequential shutdown
It is possible to optimise backup time by shutting down non-priority equipment or sequencing the
shutdown of several devices.
Two shutdown criteria are possible:
1. Shutdown of outlets after a set battery back-up time (ShutOff Delay, programmable in UM-
Console, UM-Vision)
2. Shutdown of outlets at a given battery discharge level (ShutOff Level, programmable in UM-
Vision)
It is possible to specify values for both criteria. The first criterion reached will initiate server shutdown.
4.1.3.2 Sequential
startup
It is possible to delay outlet power-on to reduce inrush currents on startup or to sequence the startup
of several devices.
Outlet startup after a given time is based on startup of the main outlet (Restart delay, programmable in