8.5
ASSEMBLING THE CRUSHER
Lift the upper and intermediate frame
(together ab. 3500 kg / 7700 lbs) and place on
lower frame. Be careful not to damage the top
bearing seal (figure 8.5.1).
Place the mounting bolts and nuts (figure
8.5.2) (20 pcs), M36/keyhole 55 mm,
tightening torque 2314 Nm (236 kpm / 1710 ft
lbs), between the intermediate and lower frame
and tighten them evenly. When lowering the
upper frame on the lower frame, the gap of
2...4 mm (1/16"-1/8") should remain between
the frame flanges. This gap must then be
closed by tightening the bolts. No clearance is
allowed between the frames.
Fill the top bearing housing with grease (figure
8.5.3). See the lubricating instructions in
chapter 6.2.
Check the condition of the o-ring and cover.
Repair or replace as necessary. Install the
cover and with bolts (4 pcs) M20/keyhole 30
mm, tightening torque 382 Nm (39 kpm / 280
ft lbs).
Check the condition of the feed chute and
repair as necessary. Install the chute with bolts
(8 pcs) M20/keyhole 30 mm, tightening torque
382 Nm (39 kpm / 280 ft lbs).
Test operate the crusher for some hours
without load to check, that it is running
properly.
Figure 8.5.2 Frame mounting bolts and nuts
Figure 8.5.3 Fill the top bearing housing
with grease
Figure 8.5.1 Lift the intermediate and upper
frame together on the crusher