55
PROVENO E
Rev. 1.2 (24.08.2016)
Installation
1
2
3
4
5
1
1. Supply cable
2. Lead-through plate
3. Cable bushing
4. Mains switch
5. N and PE terminals
Detach the lead-through plate (2) from the pillar. Slip the supply cable (1) through the cable bushing (3)
of the lead-through plate and upwards via the lead-through of the electrical box behind the mains switch
(4) to the top terminals. Connect the phase wires of the cable to the mains switch and N and PE cables
(5) to the terminal blocks.
After that, check phase order to make sure that the mixer and tilting motors rotate in the correct direction.
Close the lid and safety grid of the combi-kettle, but do not put the cover of the safety grid on.
Turn the mains switch to position I and switch the combi-kettle on with the ON/OFF switch.
Start the mixer by fi rst pressing the mixing function button and after that the mixer start button .
The mixer should rotate clockwise.
Stop the mixer by pressing the red STOP button.
On hydraulically tilted Proveno 200, 300 and 400 combi-kettles, you still have to check the rotation direc-
tion of the hydraulic pump motor.
Open the kettle lid and tilt the kettle by pressing the tilting button.
The correct rotation direction is anticlockwise viewed from the motor’s cooling fan end. An arrow indica-
ting the rotation direction is fi xed to the motor on the same side where the connection box is located.
If the rotation direction in two foregoing points is wrong, two phases of the supply cable coming to the
mains switch have to be exchanged.
Tighten the screws of the cable connections and the cable bushing properly, refi t the lead through plate
and the rear cover plate.