Page 34
Ttan Boom
TM
60-S - Operator’s Manual
September 2020
Secton 7 - Operatng Instructons & Functon Tests
3
Lift and pivot the end sections to
the stowed position�����
ART_3379
4
Lift and pivot the side sections to
the stowed position�����
ART_3380
5
Guard rails are stowed�����
ART_3381
To return the machine to normal operation mode:
Lift all rails into their upright position, then push down so secure them
Install the loading gates, spring pins and corner caps
Position the platform control box on the front rail�����
DO NOT use the machine until all gates and guard rails are in position and properly secured�����
•
•
•