52
Delivery KAS 30ME MC-Control
Transport/Set-up/Start-up
Final check of the protective devices
6.7
Final check of the protective devices
After installing the machine, be absolutely certain to carry out a final check
of the protective devices.
Procedure:
Check that all covers and safety and protective devices are installed
and fully functional.
For this purpose, use the checklist for the safety and protective devices.
See Chapter “4.4 Checklist for safety and protective devices”.
6.8
Inspection after first start-up
After 20 hours of operation after the initial set-up, it is necessary to check
all belts and tapes.
Procedure:
Check the belts and tapes on correct center running and on correct ten-
sion.
If necessary, readjust these.
See chapter service/maintenance plan.
Summary of Contents for Delivery KAS 30ME
Page 1: ...Delivery Translation of the original operating manual Keep for future use KAS 30ME MC Control...
Page 9: ...Delivery KAS 30ME MC Control 5 List of contents 10 2 Disposal recycling 88...
Page 10: ...6 Delivery KAS 30ME MC Control List of contents...
Page 50: ...46 Delivery KAS 30ME MC Control Operating and display elements operating modes Operating modes...