Crossfire LCD - Installation and Programming Manual
4
Version 1.5 | Revision B | May 2012
Instalation
Once found the correct place for the panel, please follow the steps:
1.If necessary open the plastic holes for cabling pass-through.
Please do the holes carefully and in the correct places. If for
some reason you need to add more holes, remove all the
electronic on the housing to avoid damaging the
panel’s
electronics.
All the components (PCB, PSU) can be easily removed from the
plastic base by pulling them slightly.
2.Place the panel in the desired place and mark the point A.
Remove the panel and drill a hole in the wall in point A.
Place the panel in point A and mark the remaining B marks.
Remove the panel and drill in the B points.
Finally place the panel and screw it to the wall.
3.
Do the proper connections to the panel following the
installation requirements.
Please notice that all monitored circuits shall not have any
chainings.
On the last device of the circuit, you must place the end-of-line resistor so that the control panel can
monitor its condition.
RECOMENDATIONS
Please verify that there are no water or electrical ducts on the drilling locations. If you own one, please
use a duct detector tool (for both water and electrical cables).
If you don’t please check the construction blueprints to ensure that your intallati
on will not cause any
damage on the building.