INSTALLATION OVERVIEW 

 

 

This manual will walk you through the installation of the scoreboard.  While care has been taken to 

consider the many scenarios for installation, some general information applies to all.  Use this guide 
as closely as possible to ensure proper installation, as follows: 
 

 

1.  Review the product specifications below to determine your specific installation hardware. 
2. 

Determine the scoreboard’s location and orientation. 

3.

  Install the mounting poles/I Beams (supplied by the customer).

 

4.  Mount the scoreboard to the poles/I Beams. 
5.  Install Sport Panel attachments. 
6.  Install the control cable for cable-controlled systems (

not necessary for Wireless Remote 

Control systems).  

7.

  Install the electrical service for the scoreboard and the controller.

 

8.  Install any options, such as sponsor panels or protective nets, according to the installation 

instructions included with each option package. 

9.  Test the installed system. 

10.

 Fax/return warranty activation sheet to Scoreboard Service Company at (270) 753-3773.   

 

 

   

PRODUCT SPECIFICATIONS 

 

Overall Dimensions: 

 

 

Main Cabinet -

 

48” tall x 72” long x 8” deep; shipped in two (2) sections 

 

 

 

Weight:   

 

 

Hanging weight = approximately 300 lbs   
Shipping weight = approximately 450 lbs. 

 

Mounting Recommendations: 

 

(2) 

8”  steel  I-beams  (W8 x  31) 

OR

 

(2)  8”  OD  galvanized  steel poles (schedule  40). Total 

length determined by local codes, customer preferred mounting height, and scoreboard 
options. 

 

Power Requirements: 

 

 

Scoreboard: 

(1)  120-volt,  20-amp,  60  Hz  grounded  AC  circuit  connected  to  a  power  disconnect  switch  or   
circuit breaker (refer to the wiring diagram on page 11 for detailed instructions on determining 
the scoreboard’s power requirements – specific power requirement information is also marked 
on the scoreboard’s serial number label, located on the scoreboard) 

 

Keyboard Controller: 

(1)  120-volt,  15-amp,  60  Hz  grounded  AC  circuit  in  a  standard  duplex  outlet  (optional  if  an 
internal battery pack was purchased with the controller) 

 

 
Cable Recommendations (for cable-controlled systems only): 

 

Four conductor cable 

– 28 gauge, twisted pair (two pairs), shielded data cable. 

Summary of Contents for Legacy Series

Page 1: ...1 INSTALLATION INSTRUCTIONS FOR SMALL BASEBALL SCOREBOARD Model MSB3003L5CP...

Page 2: ...TIONS 4 DETERMINING LOCATION AND ORIENTATION 5 INSTALLING MOUNTING POLES OR I BEAMS 5 MOUNTING THE SCOREBOARD 6 INSTALLING THE SPORT PANELS 7 ATTACHING THE CRISS CROSS BATS 9 RUNNING AND CONNECTING TH...

Page 3: ...1 Keyboard carrying case 1 CD ROM including installation operation maintenance warranty and support information Cable controlled systems standard 1 20 ft control cable 1 Junction box cover with built...

Page 4: ...x return warranty activation sheet to Scoreboard Service Company at 270 753 3773 PRODUCT SPECIFICATIONS Overall Dimensions Main Cabinet 48 tall x 72 long x 8 deep shipped in two 2 sections Weight Hang...

Page 5: ...on including footer specifications above ground height and total length of the poles I beams 1 Install the two 2 mounting poles I beams supplied by the customer on the field with a 4 center spacing an...

Page 6: ...board as in the image below 3 Lift the scoreboard into place to the desired height ensuring that the scoreboard is level 4 Secure the scoreboard to the poles beams using the mounting flanges attached...

Page 7: ...4 8 braces 2 each for side panels 2 20 x 1 bolts 16 3 8 x 1 bolts 32 3 8 flat washers 16 3 8 nuts 1 Place the top Sport panel onto the scoreboard by lining up a corner at one end and slipping the pan...

Page 8: ...anel The support braces bolt to the back of the Sport panel and to the top flange of the scoreboard using 3 8 x 1 1 2 bolts flat washers and nuts 3 Install the two side Sport panels support braces and...

Page 9: ...HE CRISS CROSS BATS PARTS 1 2 handles with attached braces 2 2 barrels with attached braces 3 4 braces look like a triangle with studs for mounting the bats 4 4 20 wing nuts approximately 32 5 Self ta...

Page 10: ...e barrels to the angle brackets 3 Attach the braces on each barrel to the angle brackets and secure them 4 Attach the angle brackets on the bottom outside corners of the scoreboard the same as you att...

Page 11: ...electrical service The control cable should run from the scoreboard to a location that is within 10 feet of the scorekeeper s location and into a 2 X4 wall box NOTE IF THE WIRES IN YOUR CABLE DO NOT C...

Page 12: ...the wires in the cable as that on the wires on the back of the wall plate Follow the chart if possible but more importantly whatever the match up is at the wall plate should also be the match up at t...

Page 13: ...CE AND CONNECT IT TO THE SCOREBOARD A WATERTIGHT NON FUSIBLE DISCONNECT SWITCH A 20 AMP GROUND FAULT INTERRUPTER AND A SAFETY GROUND SHOULD BE INSTALLED FOR THE 20 AMP CIRCUIT CONNECTED TO THE SCOREBO...

Page 14: ...14...

Page 15: ...s software version When the display changes and reads SELECT DIAG MODE DIGIT TEST press ENTER The LCD will now read SEGMENT TEST SEGMENTS OFF Pressing the UP arrow located on the far right of the con...

Page 16: ...______________ Date Installation Completed _________________________________ Company or Person Responsible For Installation address phone number ________________________ This document confirms that th...