Planning guide

4

1. Planning guide

1.1 

Orientation and roof pitch

A solar system in central Europe will deliver the maximum yield 
when installed at an angle of around 30° and facing south. Devi-
ations towards the south west or south east, and a roof pitch of 
15° to 50° will reduce the output only slightly and can therefore 
also be recommended without reservation.

1.2 

Planning the roof layout

Please note that the LORENZ® trapeo system described 
here is suitable only for parallel mounting.  

Any change in 

the angle of the modules can have a detrimental effect on the 
statics and is therefore not permitted. 

!

 

Before  installing  the  mounting  system,  please  read  the                    

safety instructions in chapter 4. 

We recommend our free of charge planning software, „LORENZplaner“.

LORENZplaner gives you a carefully constructed project overview, right from the start.  Very 
easy to use and totally reliable, the software leads you through the process from identifying 

wind and snow load zones and how to enter your specific module layout to the complete struc-

tural engineering report, documenting in detail the load bearing capacity of edges and corners.

Planning the module field

With this system, modules can be mounted vertically or horizon-
tally.  When mounting horizontally, please note the clamping re-
quirements of the module manufacturer in question.  Position the 
module field such that it is at least 400 mm away from the edges 
of the roof, both on the right and on the left.  The distance from 
the ridge and the eaves should not be less than  300 mm.

For building heights of ≤ 25 m all building categories and wind 

zones and all snow zones to EUROCODE 1 permitted.

When planning systems for buildings with a ridge higher than 25 
m, or for buildings on sites which are more than 800 m above sea 
level, please contact LORENZ Montagesysteme GmbH. 

 

Summary of Contents for trapeo

Page 1: ...Installation manual LORENZ trapeo LORENZ Solar module mounting system...

Page 2: ...all the safety instructions from page 10 before installing LORENZ trapeo for the first time Also please check out any new system components and functions of our mounting system Four pre drilled holes...

Page 3: ...ons 2 1 Test modules 6 2 2 Check inverters 6 2 3 Install safety devices 6 3 Mounting 3 1 Mounting the U shaped rails 7 3 2 Laying the cables 8 3 3 Mounting the modules 8 3 4 Connecting the modules 9 4...

Page 4: ...ect overview right from the start Very easy to use and totally reliable the software leads you through the process from identifying wind and snow load zones and how to enter your specific module layou...

Page 5: ...es to positioning the clamps Planning the distance between rails Option 1 short short standard 1 3Planning the mounting system The U shaped rails are available in 3 different lengths 139511000 U shape...

Page 6: ...The equipotenti al between the mounting system and the trapezoidal sheet roof is ensured in accordance with DIN VDE standards by using thin sheet metal screws Should the building have lightning protec...

Page 7: ...h points Screw the U shaped rail into place using the screws supplied until it is tight enough to create a secure seal recommended torque max 3 Nm Make sure that all U shaped rails are running in the...

Page 8: ...ollow the mounting instructions provided by the module manufacturer in order to ensure that any war ranty rights are protected This is particularly important when it comes to the positioning of fixing...

Page 9: ...ding on the number of modules in one string several hundred volts coud be achieved This could put life at risk Connect the solar modules to each other using the connection cables provided Check that t...

Page 10: ...ailure to do so can lead to injury and other damage Please keep these safety instructions close to hand The need for professional planning Before starting to construct the solar module mounting system...

Page 11: ...ork make sure you have all the necessary safety equipment Ensure too that all those involved in the work have been provided with and are observing the relevant safety instruc tions Please find below a...

Page 12: ...ransport of the original components or LORENZ Mounting System The buyer is here by bound to cover these costs 2 WARRANTY PERIOD The warranty is valid for a period of ten years beginning on the date on...

Page 13: ...ENZ in written form 7 MISCELLANEOUS If one regulation of this warranty declaration should be or become in valid the validity of the remaining regulations of the warranty shall remain unaffected An inv...

Page 14: ...zur bernahme dieser Kosten 2 GARANTIEZEIT Die Garantie ist g ltig f r die Dauer von 10 Jahren beginnend mit dem Datum des Vertragsabschlusses f r den Erstkauf des K ufers zur Montage des Montagesystem...

Page 15: ...r Form bei LORENZ geltend zu machen 7 SONSTIGES Sollte eine Bestimmung dieses Garantieversprechens unwirksam sein oder werden bleibt die Wirksamkeit der brigen Regelungen der Garantie davon unber hrt...

Page 16: ...ysteme GmbH Alfred Nobel Stra e 7 9 50226 Frechen Tel 49 0 221 126107 0 Fax 49 0 221 126107 19 www lorenz montagesystem de E Mail info lorenz ms de For errors or omissions we assume no liability Art N...

Reviews: