MAINTENANCE AND INSPEC TIONS

Fire dampers and control mechanisms do not require routine main-

tenance.

Extraordinary maintenance (repairs) and periodic inspection opera-

tions are the responsibility of the ventilation system operator.

It is recommended to keep enough space (about 200mm) for using 

or replacing the control mechanism or for maintenance. Also provide 

the necessary space to remove the ventilation duct from the damper 

whenever necessary.

It is recommended to provide inspection hatches on both sides of 

the ducts connected to the fire damper.   

The implementation of a periodic inspection plan allows to guaran-

tee the efficiency and functionality of the fire dampers for the fire 

safety of the building.

 

„

Periodic inspection and cleaning

Periodic inspection shall be performed in accordance with the re-

quirements of the law or by the building regulations or other local 

regulations.

In the absence of specific regulations (or to their complement), in ac-

cordance with point 8.3 of the EN 1560 standard, it is recommended 

to carry out the following control activities at intervals of no more 

than 12 months:

•  Check the servomotor electrical wiring for damage (where appli-

cable);

•  Check end-switch wiring for damage (where applicable);

•  Check damper cleanliness and clean where necessary;

•  Check the condition of blades and seals, rectify and report where 

necessary;

•  Check the correct opening and closing of the fire damper by ma-

nual operation according to the instructions in the technical ma-

nual of the fire damper;

•  Check the opening and closing operation of the damper control-

led by the fire alarm system (if present);

•  Check the operation of the end switches in open and closed state, 

adjust and report if necessary;

•  Confirm that the damper fulfils its function as part of the control 

system (where necessary);

•  Check that the damper is left in its normal operating position, whi-

ch usually corresponds to the open position.

 

„

Repair

For safety reasons, repair activities involving fire-fighting componen-

ts must be carried out only by qualified personnel.

Only original spare parts supplied by the fire damper manufacturer 

must be used.

A functional test must be performed after each repair.

.

At the end of the inspection, cleaning or repair operations, check that 

the fire damper is in the normal operating position.

Keep records of all inspections, repair activities, any problems en-

countered and their resolution.

This practice, even when not mandatory, is very useful in practice.

 

„

Disposal

Disposal in case of destruction must be carried out in accordance 

with national legislation. For electrical and electronic parts also refer 

to EU Directive 2011/65.

INSTALLATION

The sizes shown are in mm.

It is recommended to perform a functional test before Installation to 

exclude possible damage during transport and another test imme-

diately after installation to exclude accidental damage to the product 

and interference with mounting components.

 

„

Blade rotation axis positioning

The fire damper can be installed with the blade axis positioned verti-

cally or horizontally or tilted at any angle.

 

„

Positioning brackets before fixing

1.  Positioning brackets

 

„

Installation of flexible connectors in order to balance out the 

ventilation ducts expansion

ATTENTION: the following indications must be considered 

binding only if legislation or local regulation where the fire 

dampers are installed require the use of flexible connectors.

Flexible connectors compensate any duct thermal expansion and 

wall bending in case of fire.

Flexible connectors are used to limit fire damper stresses due to ex-

ternal forces in case of fire and to preserve fire resistance class.

In general it is always appropriate the use of flexible connectors for 

the followings installations:

– light walls;

– Plasterboard and rock wool or Fire Batt (Weichschott) sealing;

– Applique fixing system.

Flexible connector must be normal flammability and in case of fire 

the grounding bonding should disconnet to guarantee the comple-

te separation between fire damper and connected air duct.

When flexible connectors made of conductive material (e.g. alumi-

num) are used, no additional grounding bonding is required.

Despite flexible connector installation, the fire damper must be in-

stalled in the construction support so that its weight does not affect 

damper’s installation position both during normal operation and in 

case of fire.

It is recommended not to compress flexible connectors in the in-

stallation phase.

Flexible connector must be at least 100mm long and in order that 

possible duct thermal expansions are balanced. 

Take care that the flexible connector does not interfere with opening 

/ closing movement of the blade.

 

„

Transfer Application (application not connected to air ducts on 

one or both sides)

Note: For this application please refer to national legislation to verify 

if any specific obligation is required.

Following tests performed as per EN 1366-2, section 6.3.6 Standard, 

it is possible to install the fire damper free from air duct from one or 

both sides.

•  Attention: fire resistance classification for transfer application is 

conform to section Fire resistance classification according to EN 

13501-3-2009  limited to EI 90S if the ducted classification is higher.

rev 20-10

7

We reserve the right to make changes without prior notice

Summary of Contents for WH45 Series

Page 1: ...ww mp3 italia it 1MUBWH45EN rev 20 10 1MUBWH45EN WH45 WH45 l indab we simplify co nstruc tio n www lindab com Fire dampers are manufactured by MP3 Srl www mp3 italia it 1MUBWH45EN LIND rev 20 10 1MUBW...

Page 2: ...cal light wall gypsum blocks wall Wall minimum thickness 70 mm Wall minimum density 995 kg m Plaster putty sealing ve i o W min 200 max 800 min 200 max 800 min 200 max 800 EI 120 S Installation within...

Page 3: ...ade position open or closed Refer to Electrical connections paragraph for more details Closing by remote control With power supply input or interruption magnet WH45M version only Temperature calibrati...

Page 4: ...sup plied to the motor Position indication microswitches The motorized versions are supplied with two microswitches to show the blade s position open or closed Refer to the section Electrical connect...

Page 5: ...ollows Check that the voltage and electrical frequency are equivalent to those of the motor of the servomotor check the motor s informa tion label Make the connections as shown in the below diagram 1...

Page 6: ...W Motor 230V AC WH45DPS WH45DSS Siemens GNA326 GRA326 Opening 4 5 W In stand by 3 5 W 24V AC DC motor WH45VGS Siemens GGA126 Opening 6 W In stand by 1 5 W 230V AC motor WH45DGS Siemens GGA326 Opening...

Page 7: ...ance with national legislation For electrical and electronic parts also refer to EU Directive 2011 65 INSTALLATION The sizes shown are in mm It is recommended to perform a functional test before Insta...

Page 8: ...echanism side 2 Mechanism opposite side 3 End cap with mesh L1 End cap length mechanism side L2 End cap length mechanism opposite side Fire damper nominal diameter Length of end cap with mesh dependin...

Page 9: ...floor Installation a mm b mm c mm d mm Rigid wall EI 90 S Installation within vertical rigid wall Plasterboard and rock wool 100 kg m sealing 50 75 EI 120 S Installation within vertical rigid wall Mor...

Page 10: ...pacing of 625 mm between each other vertical profile fixing with selfthreading screws or by clinching to the bottom horizontal profile and insertion in the top horizontal profile profiles fixed using...

Page 11: ...ol lowing characteristics minimum thickness 100 or 150 mm according to the resistance class required minimum density 2200 kg m Installations within vertical rigid wall Refer to the section Constructio...

Page 12: ...for further information Wall opening A opening must be provided in the wall as indicated in the table and in the drawing Damper positioning Position the damper in the opening so that the side of the...

Page 13: ...l as indicated in the table and in the drawing Damper positioning Position the damper in the opening so that the side of the closing mechanism extends as indicated in the table and in the drawing Clos...

Page 14: ...he drawing Sealing with concrete is not allowed Fire resistance classification D hole size mm Damper protrusion from the floor E mm Floor minimum thickness S mm Sealing EI 90 S Installation within flo...