Lift the safety prop, move it to the center of the scissor sleeve center and rotate it upward until it is
vertical.
③
Lower the platform height until the safety prop completely contacts the shaft sleeve.
Warning: crush hazard
Be sure to put your hand on correct position of the safety prop when lowering the platform.
④
Open the limit switch base cover on the chassis.
⑤
Slightly raise the platform and recover the safety prop to the installation position.
⑥
Lift the platform via the ground controller, while pressing the upper limit switch arm to initialize the
upper limit switch.
Result: the platform stops rising and the function of machine is normal.
Result: the platform continues to rise. Adjust or replace the upper limit switch.
12.11
Steps of checklist C
C-1
Test of platform overload system
1) This step shall be made once per 500h or per 5 months, whichever is shorter. Or the check and re
calibrate shall be made immediately when the overload failure appears.
Calibration Method
No load:
1: Turn the key switch to Platform Mode; (note: the platform is in stowed position at the very
beginning)
2: Move the LIFT button as described below to activate the no-load automatic weighing procedure:
“DOWN” “DOWN” “DOWN” “DOWN” “DOWN” (5 times) “UP”
“DOWN” “DOWN” “DOWN” “DOWN” “DOWN” (5 times) “UP”
“DOWN” “UP” “DOWN” “DOWN” “DOWN”
Attention:
a. Each operation of the button shall last for 0.15s – 2.5s;
b.
The calibration will be terminated when any operation of the button exceeds the limit,
and in this case, the calibration shall be performed again from the very beginning.
c.
After the horn sounds 5 times, it suggests that the machine has entered the calibration
procedure correctly.
d.
When the platform covers the whole travel and stops at the bottom, and the horn stops
sounding, it suggests that the calibration has been finished successfully.
Full load:
1: Load the platform: Place the counterweight (1.1 times of the rated load) at the center of the
machine platform;
2: Turn the key switch to Platform Mode; (note: the platform is in stowed position at the
very beginning)
3: Move the LIFT button as described below to activate the full-load automatic weighing
procedure:
67
Summary of Contents for S0507SDTCE10
Page 5: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 1 Safety 1...
Page 11: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 2 Legend 7...
Page 12: ...Operation and Maintenance Manual of Aerial Work Platform 8...
Page 14: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 3 Label 10...
Page 15: ...Operation and Maintenance Manual of Aerial Work Platform 11...
Page 16: ...Operation and Maintenance Manual of Aerial Work Platform 12...
Page 18: ...Operation and Maintenance Manual of Aerial Work Platform 14...
Page 19: ...Operation and Maintenance Manual of Aerial Work Platform 15...
Page 21: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 4 Specification 17...
Page 24: ...Operation and Maintenance Manual of Aerial Work Platform 20...
Page 25: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 5 Controller 21...
Page 37: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 6 Emergency operation 33...
Page 40: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 7 Pre operation inspection 36...
Page 43: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 8 Workstation inspection 39...
Page 45: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 9 Function test 41...
Page 49: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 10 Operation notice 45...
Page 56: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 12 Maintenance 52...
Page 76: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 13 Schematic diagram 72...
Page 77: ...Operation and Maintenance Manual of Aerial Work Platform Electric schematic diagram 73...
Page 78: ...Operation and Maintenance Manual of Aerial Work Platform Hydraulic schematic diagram 74...