④
Press the drive function selector button.
⑤
Select one point (such as the touchdown point on the wheel) from the machine as the visual
inspection reference of the test line.
⑥
Drive the machine at the maximum speed and release the handle at the moment when the
reference point passes the ground test line.
⑦
Measure the distance between the reference point and the survey line.
Result: the machine is stopped within the specified braking distance. No action is required.
Result: the machine is not stopped within the specified braking distance.
△
!
Notice: the brake must be valid within the allowable gradeability range of the machine.
⑧
Replace the brake and repeat the process above from Step 1.
B-8
Test of driving speed-folding status
1)
This check shall be made once per 250h or per season, whichever is shorter.
2)
The normal driving function is essential to the operation safety. With the driving function, a rapid
and stable response shall be given to the operator. No delay, vibration and abnormal sound shall
be outputted during the normal operation and driving process.
3)
Be sure to complete the driving test on a firm and level ground without any barrier.
①
Draw two lines, spaced by 10m on the ground, as the starting line and the finishing line.
②
Switch the key switch to the platform controller and draw out the red emergency stop buttons from
the ground and platform controller.
③
Lower the platform to the folding position.
④
Press the drive function selector button.
⑤
Select one point from the machine as the visual inspection reference for the starting line and the
finishing line.
⑥
Drive the machine at the maximum speed and start to count when the reference point passes the
starting line.
⑦
Keep driving at the full speed and record the time when the reference point passes the finishing
line. Refer to the specification.
B-9
Test of driving speed-lifting status
1)
This check shall be made once per 250h or per season, whichever is shorter.
2)
The normal driving function is essential to the operation safety. With the driving function, a rapid
and stable response shall be given to the operator. No delay, vibration and abnormal sound shall
be outputted during the normal operation and driving process.
3)
Be sure to complete the driving speed test on a solid and level ground without any barrier.
①
Draw two lines, spaced by 10m on the ground, as the starting line and the finishing line.
②
Switch the key switch to the platform controller and draw out the red emergency stop buttons from
the ground and platform controller.
③
Press the lifting function selector button.
62
Summary of Contents for S0507SDTCE10
Page 5: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 1 Safety 1...
Page 11: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 2 Legend 7...
Page 12: ...Operation and Maintenance Manual of Aerial Work Platform 8...
Page 14: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 3 Label 10...
Page 15: ...Operation and Maintenance Manual of Aerial Work Platform 11...
Page 16: ...Operation and Maintenance Manual of Aerial Work Platform 12...
Page 18: ...Operation and Maintenance Manual of Aerial Work Platform 14...
Page 19: ...Operation and Maintenance Manual of Aerial Work Platform 15...
Page 21: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 4 Specification 17...
Page 24: ...Operation and Maintenance Manual of Aerial Work Platform 20...
Page 25: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 5 Controller 21...
Page 37: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 6 Emergency operation 33...
Page 40: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 7 Pre operation inspection 36...
Page 43: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 8 Workstation inspection 39...
Page 45: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 9 Function test 41...
Page 49: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 10 Operation notice 45...
Page 56: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 12 Maintenance 52...
Page 76: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 13 Schematic diagram 72...
Page 77: ...Operation and Maintenance Manual of Aerial Work Platform Electric schematic diagram 73...
Page 78: ...Operation and Maintenance Manual of Aerial Work Platform Hydraulic schematic diagram 74...