evr-green
™
Level
2 -
Network Charging Station For Public Applications
www.leviton.com/evrgreen • 1-877-338-7473 • [email protected]
Step 6 - Connect wires to wiring terminals
Pull the 240V L1, L2, and Ground wires
into body assembly and connect to
wiring terminals.
Strip wires ¼” (6 mm), insert in
terminal block, and tighten screws to
18.5 inch-lbs (2.1 Nm).
IMPORTANT:
• requires a dedicated 40A breaker.
• Use copper conductors only.
• Do NOT provide GFCI protection at
panel. The Evr-Green Level 2
Public Use Station has built-in
GFCI protection.
• In areas with frequent thunder
storms, add surge protection at the
service panel for all circuits.
TIP:
To make it easier to connect the wires, you
can remove and replace the terminal block. To
do so, simply loosen the two mounting screws
holding the terminal block to the body a few
turns. Then slide the terminal block up and off
the screws. Insert the wires and tighten the
wiring screws as described above. Then, slide
the terminal block back over its two mounting
screws, and tighten the mounting screws.
You have now finished installing the
Pole Mounting assembly for the Evr-Green
Level 2 Public Use Station. You are ready to
install the holster and cable assembly.
See Chapter 5.
Use these 3 screws
3-7