TRANSPORT - HANDLING
FORKLIFT PROTECTIONS
PRELIMINARY CHECKS
Before installing the equipment, the following points MUST
be checked :
-Have the forklift protections been removed ?
-Is there sufficient space for the equipment?
-Is the surface on which the equipment is to be installed
sufficiently solid to withstand its weight? A detailed study of
the frame must be made beforehand.
-Do the supply and return ductwork openings excessively
weaken the structure?
-Are there any obstructing items which could hinder the
operation of the equipment?
-Does the electrical power available correspond to the
equipment's electrical specifications?
-Is drainage provided for the condensate?
-Is there sufficient access for maintenance?
-Installation of the equipment could require different lifting
methods which may vary with each installation (helicopter or
crane). Have these been evaluated ?
-Ensure that the unit is installed in accordance with the
installation instructions and local applicable codes.
-Check to ensure that the refrigerant lines do not rub against
the cabinet or against other refrigerant lines.
In general, make sure no obstacles (walls, trees or roof ledges)
are obstructing the duct connections or hindering assembly
and maintenance access.
REMOVE FORKLIFT PROTECTIONS
BEFORE INSTA
L
LATION
INSTALLATION REQUIREMENTS
The surface on which the equipment is to be installed must
be clean and free of any obstacles which could hinder the
flow of air to the condensers:
-Avoid uneven surfaces
-Avoid installing two units side by side or close to each other
as this may restrict the airflow to the condensers.
Before installing a packaged Rooftop unit it is important to
understand :
-The direction of prevailing winds.
-The direction and position of air flows.
-The external dimensions of the unit and the dimensions
of the supply and return air connections.
-The arrangement of the doors and the space required to
open them to access the various components.
CONNECTIONS
-Ensure that all the pipe-work crossing walls or roofs are
secured, sealed and insulated.
-To avoid condensation problems, make sure that all pipes
are insulated according to the temperatures of fluids and
type of rooms.
NOTE: The AQUILUX protection sheets fitted to the finned
surfaces must be removed prior to start up.
Fig. 9
Summary of Contents for Baltic BCK 020
Page 1: ...BALTIC English August 2003 INSTALLATION OPERATING MAINTENANCE MANUAL ...
Page 38: ...IOM ROOFTOP BALTIC Series 0803 E Page 37 VENTILaTION AIRFLOW BALANCING 020 025 Fig 37 ...
Page 39: ...Page 38 IOM ROOFTOP BALTIC Series 0803 E VENTILaTION AIRFLOW BALANCING 035 030 Fig 38 ...
Page 40: ...IOM ROOFTOP BALTIC Series 0803 E Page 39 VENTILaTION AIRFLOW BALANCING 045 050 040 Fig 39 ...
Page 101: ...Page 100 IOM ROOFTOP BALTIC Series 0803 E EC declaration of conformity ...
Page 102: ...IOM ROOFTOP BALTIC Series 0803 E Page 101 EC declaration of conformity ...
Page 103: ...Page 102 IOM ROOFTOP BALTIC Series 0803 E EC declaration of conformity ...
Page 104: ...IOM ROOFTOP BALTIC Series 0803 E Page 103 EC declaration of conformity ...
Page 105: ...Page 104 IOM ROOFTOP BALTIC Series 0803 E EC declaration of conformity ...
Page 106: ...IOM ROOFTOP BALTIC Series 0803 E Page 105 EC declaration of conformity ...
Page 108: ...IOM ROOFTOP BALTIC Series 0803 E Page 107 EC declaration of conformity ...
Page 109: ...Page 108 IOM ROOFTOP BALTIC Series 0803 E EC declaration of conformity ...