GS10/GS15, Operation
28
Equipment setup
step-by-step
Step
Description
1.
Set up the tripod.
2.
Mount and level the tribrach on the tripod.
3.
Ensure that the tribrach is over the marker.
4.
Place and lock the carrier in the tribrach.
GS10
GS15
5.
Screw the GNSS antenna onto the
carrier.
Insert the data storage device and
the batteries into the GS15.
6.
Check that the tribrach is still level.
Screw the GS15 onto the carrier.
7.
Insert the batteries into the instru-
ment.
Check that the tribrach is still level.
8.
Insert the SD card into the instru-
ment.
Insert the data storage device and
the battery into the field controller.
9.
Connect the instrument to the GNSS
antenna using the antenna cable and
port ANT on the instrument.
-
10.
Switch on the field controller and connect it to the instrument if necessary.
11.
To hang the instrument on the tripod
leg, use the hook on the rear of the
unit. Or place the instrument in the
container.
To hang the field controller on the
tripod leg, use the hook on the hand
strap or use the utility hook. Refer to
the User Manual of the field
controller.
12.
Insert the height hook into the carrier.
13.
Measure the antenna height using the height hook.
14.
Press the ON/OFF button on the instrument for at least 2 s to switch on the
instrument .