Understanding Stake and Check Basics
11.7.3
Slope Staking Using a Reference Point
Description
When staking out slopes using the reference point method, the catch point of the slope is
marked with a reference peg using a defined offset. The grade of the slope is marked and
controlled by "grade checkers".
The reference point offset guarantees that all pegs are placed with the same horizontal offset
to the catch point.
Workflow
a) Slope to stake out
b) Natural surface
c) Catch point of the slope
d) Defined reference point offset
Ref Offset
e) Reference peg
RR12_022
a
c
b
d
e
a) Slope to stake out
b) Natural surface
c) Real catch point
d) Projected catch point
e) Approximate staked out catch
point after three iterations
f) Defined reference point offset
Ref Offset
g) Reference peg
RR12 023
a
c
b
d
e
g
c
d
f
1
2
Summary of Contents for RoadRunner
Page 1: ...Leica RoadRunner Technical Reference Manual Version 5 0 English ...
Page 15: ...Step 1 RoadRunner Begin RoadRunner 15 ...
Page 35: ...Step 3 Working in Standard mode RoadRunner 35 ...
Page 121: ...Step 4 Measuring RoadRunner 121 ...
Page 158: ...158 RoadRunner Configuring Screen ...
Page 164: ...164 RoadRunner Configuring Next step CONT F1 to confirm the changes and continue ...
Page 191: ...Configuring RoadRunner 191 ...
Page 201: ...Managing the Project RoadRunner 201 ...
Page 223: ...Viewing and Editing the Design Data RoadRunner 223 ...
Page 251: ...Working with the Extras Menu RoadRunner 251 ...
Page 335: ...Quick Start Tutorial Advanced Mode RoadRunner 335 ...
Page 340: ...i 340 RoadRunner Index ...
Page 341: ...Index RoadRunner i 341 ...