OMEGA
Installation Manual
Edition Dec. 2004
Omega
platform lift
page 17 of 24
Set up a ground connection if required.
•
Mount the Call Stations, starting with the Call Station at the lowest landing.
•
When mounting the Call Station, remember to allow enough clearance for the carriage at
the lower landing. The height of each Call Station should be 1 m, measured from the
floor to the centre of the Call Station.
•
Wire the Call Stations according to the electrical drawings.
•
On outdoor lifts, install the hood that is supplied with each Call Station.
•
If the Call Station is supplied with a pedestal, ensure that the pedestal is plumb before
mounting the Call Station.
•
Connect the current collector with the “Ra” and “Sa” connections in the control cabinet as
shown in the picture below. (The current collector is also shown on page 7.)
Ra
Sa
Current
collector