drawing two parallel lines (1# and 2#) on the
concrete floor, the tolerance should less than 3mm
(0.1”).
Draw four parallel lines (a, b, c, d), vertical with 1#
and 2#.
Follow the drawing, put two platforms into the frame.
Warnings:
The base is the edge of Floor plate.
The tolerance should less than 6mm (0.24”)
Drawing the frame is very important. Poor drawing will
cause many problems about assembly and operation.
5.3 Control Desk Installation
Place the control desk in place according to the
ground layout.(Fig.6)
Use cover plate to protect the wires if there is no
wire channel on the concrete floor.
Fill hydraulic oil N32 or N46 (approximate 20L) into
he oil tank (using oil dipstick to check the level).
Pay special attention to avoid dust and contaminants
into the oil.