1   General Information

1.4

Terms and Definitions

For further explanations of terms and definitions see IEC 61508-4 (or DIN EN 61508-4).

DC

Diagnostic coverage 

DC

AVG

Average diagnostic coverage 

E/E/PE-System 

Electrical/electronic/programmable electronic system 

EUC

Equipment under control 

FIT

Failure In Time in 10

-9

 1/h

FMEDA

Failure Mode, Effects, and Diagnostics Analysis

λ

s

Probability of safe failure (detected and undetected)

λ

d

Probability of dangerous failure

λ

dd

Probability of dangerous detected failure

λ

du

Probability of dangerous undetected failure

λ

no effect, 

λ

don’t care  

Probability of failures with no effect (not used in SFF calculation)

HFT

Hardware fault tolerance

MooN

M out of N channel architecture

MTBF

Mean time between failures

MTTR

Mean time to repair

MTTF

Mean time to failure

PFD

Probability of dangerous failure on demand (Low Demand mode)

PFD

AVG

Average probability of dangerous failure on demand

PFH

Average frequency of a dangerous failure per hour (Continuous mode)

PTC

Proof Test Coverage, proportion of detectable unsafe failures

SFF 

Safe failure fraction 

SIF

Safety instrumented function 

SIS

Safety instrumented system 

SIL

Safety integrity level

SIL AC

Safety integrity level architectural constraint

SC

Systematic Capability

T

1

Proof test interval

T

2

Diagnostic test interval

                                      

T

2 IBD

                        Interval between demands of the safety function 

Summary of Contents for F200K2 IR-1

Page 1: ...www lamtec de Sensors and Systems for Combustion Engineering Safety Manual F200K...

Page 2: ......

Page 3: ...fe State 7 2 4 Scope of Application 7 2 5 Additional Components 7 2 6 Safety Values 8 2 7 Life time 9 3 Installation and Commissioning 10 3 1 Verification 10 4 Operation 12 4 1 Proof Test 12 4 2 Proof...

Page 4: ...of the device The plant operator is responsible for the correct execution of these operations NOTICE The Safety Manual does not replace the operating and installation manuals of this device It contain...

Page 5: ...emperature range as defined in Appendix see chapter 7 2 Hints and require ments for installation commissioning operation and verification leads to a loss of the safety integrity and may cause personne...

Page 6: ...ttention to the possibility of imminent danger If it is not avoided it may result in death or very serious injury The plant including its surroundings could be damaged CAUTION This draws the user s at...

Page 7: ...robability of failures with no effect not used in SFF calculation HFT Hardware fault tolerance MooN M out of N channel architecture MTBF Mean time between failures MTTR Mean time to repair MTTF Mean t...

Page 8: ...pses in the event of modifications to the unit The unit s inputs and outputs must be wired according to the specifications in the instruction manual only DANGER The appendix Hints and requirements for...

Page 9: ...el drift have been used Under special circumstances short circuits have not to be assumed Estimation of common cause factors 2 D 1 The Proof test interval T1 is equivalent to the product mission or li...

Page 10: ...EN 61511 see 2 4 Scope of Application 3 SFF is relevant for elements subsystems or systems in a complete safety loop This device is always part of a com plete safety loop A SIL calculation of a safety...

Page 11: ...components remains still active DIN EN 61508 2 2011 Note N3 gives the hint that appropriate measures taken by the manufacturer and plant operator can extend the useful lifetime The burner control is d...

Page 12: ...he flame detector e g According to EN 61558 2 6 or EN 60950 1 WARNING Use a floating contact which is feeded by the flame detector s 24 V supply for the remote switching of the F200K2 s range Or use a...

Page 13: ...l for shutting off the safety valve is trig gered off within the period of TS 1 s on safety period Operation at tVOff 1 s after extinc tion of the flame Red LED lights Green LED dark For the IR compac...

Page 14: ...operation and decrease the average probability of dangerous failure on demand PFDAVG during the defined mission time According to DIN EN 61508 2011 6 the PFDAVG can be calculated by the use of a proof...

Page 15: ...d completely dangerous voltages can be applied at the cable contacts To execute a basic proof test with a PTC of 70 for the F200K series the following test steps must be executed and approved Disconne...

Page 16: ...ured while the device is being repaired or a maintenance is ongoing After a repair or a maintenance follow chapter 3 Installation and Commissioning again WARNING Replace the device only by one of the...

Page 17: ...uctions from the installation manual and ensure the safe operation of the application after that The device should be replaced after the product s mission or life time see chapter 2 7 Life time The de...

Page 18: ...17 7 Appendix 7 Appendix 7 1 T V Confirmation...

Page 19: ...18 7 Appendix...

Page 20: ...19 7 Appendix 7 2 Hints and requirements for installation commissioning operation and verification...

Page 21: ...20 8 EU Declaration of Conformity 8 EU Declaration of Conformity...

Page 22: ...21 8 EU Declaration of Conformity...

Page 23: ...22 8 EU Declaration of Conformity...

Page 24: ...KG Wiesenstra e 6 D 69190 Walldorf Telefon 49 0 6227 6052 0 Telefax 49 0 6227 6052 57 info lamtec de www lamtec de Publication no DLT7604 19 aEN 006 The information in this publication is subject to t...

Reviews: