Installation 

 

 

Pre-Installation Information  

General Information 

The H Series Tankless Water Heater provides instant and precise temperature-controlled hot water. To ensure proper 

performance, install the heater according to the following installation instructions and in compliance with applicable 

national and local codes. 
Flow rates and temperature figures are important for proper sizing If needed to meet certain temperature demands, 

flow control devices are readily available See temperature rise table for specifications Contact Laars representatives for 

further information on available flow control devices

.  

Operation and Setup 

H Series heaters supply an unlimited amount of hot water with specific flow and temperature rise capabilities. These 

heaters are energy efficient, reliable, and provide optimum performance in the most demanding applications.  

Application Specific Requirements  

The H Series can be used in many different applications that require custom tuning for specific applications to maximize 

performance of the heater.  
For use in a re-circulation loop, the incoming loop temperature should not exceed 140°F (60°C). 
For applications utilizing quick close valves or solenoid valves, it is important to install a hammer arrestor or surge tank 

close to the point of use to absorb pressure spikes.  

Installation Considerations  

Maximum operating pressure: 150 psi (10 bar)  
ASME maximum operating pressure: 160psi (11 bar) 
Standard flow activation:  1.5 gpm (5.7 lpm) 

Certifications  

Electric Tankless Water Heaters are certified by ETL to UL499, cETL listed to CSA-C22 2 No 88 and third party certified to 

NSF/ANSI 372.  

WARNING For safe operation of the heater, observe all the warning labels as indicated.

 

 

Storage Instructions  

NOTICE! Keep Electric Tankless Water Heaters stored in original packaging until installation.  

Recommended storage criteria:  

Store Electric Tankless Water Heaters where temperatures exceed 35°F (2°C) at all times. 
Indoor storage is recommended. 
Minimize excessive on-site transport to reduce risk of shock and impact damage.  

Packaging 

 

Box dimensions approx: 30" x 15" x 6" (762mm x 381mm x 152mm)  

All boxes must be stacked evenly and horizontally. 

Safety issues related to packaging:  

 

Product should be transported with the care associated to packages labeled “FRAGILE” even if packaging is not 

marked accordingly.  

 

Standard safety procedures for forklift transport and large items less than 1000lbs (454 kgs) should be followed at 

all times. 

Summary of Contents for H Series

Page 1: ...TEH006 LCTEH010 LCTEHV010 LCTEH015 LCTEHV015 LCTEH018 LCTEHV018 LCTEH025 Voltage options 208V Single Three Phase 240V Single Three Phase 277V Single Phase 380V Three Phase 400V Three Phase 415V Three...

Page 2: ...allation 6 7 Electric Installation 8 Start Up Check List 9 Start Up 10 Digital Controller Operation 11 NEMA 4 4X Digital Controller Operation 12 Perform Operational Test No 1 13 Perform Operational Te...

Page 3: ...nnect power supply before performing any work in the enclosure Failure to ground this system may result in death or serious injury Make sure that all water supply lines have been flushed and then comp...

Page 4: ...0 F 60 C For applications utilizing quick close valves or solenoid valves it is important to install a hammer arrestor or surge tank close to the point of use to absorb pressure spikes Installation Co...

Page 5: ...and other plumbing for service maintenance Set heater in a vertical upright position with the water outlet located at top Depending on the application the unit may also be installed rotated clockwise...

Page 6: ...any drop to eliminate trapped air Install one union on the water inlet side of the heater and another union upstream of the 100 Mesh 150 micron y strainer Install one union on the water outlet side of...

Page 7: ...Installation 7 2 Plumbing Installation cont...

Page 8: ...Table 310 15 for 75 C insulated copper wire 30 C Ambient Aluminum wire requires larger gauges Not all available optional voltages are listed in the table For standard enclosures remove the four screws...

Page 9: ...nstalled after pressure and temperature relief valve on outlet if required by local or national plumbing codes If the hot water process is not at the highest point in the plumbing loop then an automat...

Page 10: ...ge elements and cause heater malfunction Turn on the connected process observe output temperature rise to setpoint On standard controller set point and output temperatures are located side by side On...

Page 11: ...the controller Keys and Displays Function Setpoint Up and Down Buttons In the Home Page adjusts the set point in the right display In other pages changes the upper display to a highter or lower value...

Page 12: ...e of the controller Keys and Displays Function Setpoint Up and Down Buttons In the Home Page adjusts the set point in the right display In other pages changes the upper display to a highter or lower v...

Page 13: ...he inlet water temperature is equal to or greater than the temperature set on the digital controller 9 Perform Operational Test No 2 Each model has precise specifications for temperature rise capabili...

Page 14: ...tuation FDS Fused Disconnect Internal fused disconnect interlocks with enclosure door when energized prohibiting access to a live cabinet Select the FDS option for an additional level of safety and co...

Page 15: ...ere hard water sediment is present in the water To clean the Y Strainer 1 Turn the power off at the circuit breaker panel 2 Shut off the installer supplied cold water isolation valve to the heater 3 R...

Page 16: ...mperature or faulty sensor Turn power off Check for loose or disconnected wires Check the incoming service connection Voltage must match name plate rated voltage Labels are located on the upper left o...

Page 17: ...urce A load voltage reading is also helpful Turn power OFF before recording any Ohm readings If the above steps do not solve the problem some additional checks may be performed Follow the schematic to...

Page 18: ...DC Option Pin Out D1 Option Pin Out Pin Name Description Pin Name Description T R 2 RS 485 Transmit Receive Non Inverting Input Output Negative 3 Return Current Path for Current Pin 4 3 Signal Ground...

Page 19: ...UINT RWES Remote Set Point Control Mode Process Value 1999 000 to 9999 000 F 1128 000 to 5537 000 C 402 402 Float R Process Value Control Mode OFF 62 Auto 10 Manual 54 1880 2360 Auto UINT RWES Contro...