3�1 Starting and Shutting Down
This section describes how to start and shut down DRYPRO 832.
Leave the power supply circuit breaker on during normal use.
Power supply circuit breaker
Operation Switch
3�1�1 How to Start
First, start Printlink5-IN or console, and then DRYPRO 832. Perform the following steps.
1
Turn on the DRYPRO 832 power supply circuit breaker�
If the power supply circuit breaker is already turned ON, go to the next step.
Power supply circuit breaker
2
Press the operation switch until a beep sounds (about one second)�
Operation Switch
Pressing the operation switch again shuts down� In such a case,
press the operation switch again�
Initialization and warm-up of DRYPRO 832 will start. Upon completion of the warm-
up, the machine is ready to print.
Summary of Contents for Drypro 832
Page 1: ...LASER IMAGER 01 ET EN ...
Page 2: ......
Page 4: ...4 Sisukord Appendix 75 A Specifications 76 B Test Print Check List 78 ...
Page 9: ...9 Peatükk 1 Hoiatused ja ettevaatusabinõud ...
Page 25: ...25 Chapter 2 Product Outline ...
Page 33: ...33 Chapter 3 Operation from Main Unit ...
Page 53: ...53 Chapter 4 Troubleshooting ...
Page 63: ...63 Chapter 5 Maintenance ...
Page 75: ...75 Appendix ...
Page 80: ...80 ...
Page 81: ...81 ...
Page 82: ...82 ...
Page 83: ......