Install Main Pivot Link and
Master Cylinder
Attach the master cylinder with the pins provided.
The rod clevis attaches to the lug on the main pivot
link.
The butt end of the cylinder attaches to the lug in the
centre of the top cross frame.
Remove the protective port plugs so the cylinder
can be moved in or out during the assembly of the
remaining self levelling linkages.
Main Pivot Link
Install the 10' (3m) main pivot link with the long pin provided. When the main link is in place install
the 4-1/2" x 8" master cylinder as shown in the detail below. Be sure to install the stop collar kit on the
cylinder rod. Do not install the other linkages until both the main pivot link and cylinder are in place.
(The pivot link may have been installed at the factory)