19.1 Applying DC Power to the Inverter
To apply DC power to the inverter:
1. Before applying DC power to the inverter, measure the voltage and check polarity at
all connections. Measure at the battery side of the disconnect or breaker.
2. Apply battery (DC) power to the inverter by closing the battery bank DC disconnect.
The inverter will power up in standby mode, and the inverter informa-
tion panel will display Stb(standby), as shown in Figure below.
Enabling the Inverter
Invert mode is enabled by default, and the Conext XW Pro should begin inverting upon tran-
sitioning from standby mode. If invert mode is disabled, the inverter information panel will
display "---" once out of standby mode.. If the Conext XW Pro powers up in standby mode,
press the STARTUP/SHUTDOWN button momentarily to change the mode from standby to
operating.
On the inverter information panel, simultaneously press the STARTUP/SHUTDOWN button and
the Equalize button. The Conext XW Pro is now enabled, and En (enabled) is briefly displayed on
the inverter information panel, as shown in Figure
For information about operating the Conext XW Pro Inverter/Charger, see the Conext XW Pro Inverter/Charger Owner’s Guide (975-0240-01-01).