Start-Up Procedure
9.01. The following paragraphs provide instructions for applying power to the system,
performing initialization, and verifying basic system functions. These procedures
should be completed before the system is initialized and the database is changed by
system programming to include the customers requirements.
Power-Up Procedure
9.02. Before applying power to the system, ensure that all Installation Configuration
changes have been made and switches and straps are in proper position. Also
check the interior that no loose or frayed wiring is present. All stations and trunk
lines should be connected and wiring checked for circuit continuity.
9.03. To power up the system following installation:
1) Set the power 0/1 switch to the off, '0' position. (Refer to Figure 5)
The P.L. indicator lamp (red) is off.
2) At the AC wall receptacle and at the power receptacle on the bottom of
the main cabinet, plug in the power supply cord.
3) Set the power 0/1 switch to on, '1' position. Observe the following:
l
P.L. indicator lamp (red) is on. (Refer to Figure 5)
l
Memory protection indicator on. (Refer to Figure 14)
l
Micro-processor scan indicator is flashing.
l
Trunk idle/busy status indicators are off.