14
Installation and Servicing
SECTION 1 - GENERAL
Model 30
Max CH uutput
kW
30.3
Water flow rate l/min
21.5
(gal/min)
(4.7)
Temp differential
o
C
20
Head available m.w.g.
1.9
for system
(ft.w.g.)
(6.2)
General
1.
The installation must comply with all relevant national and local
regulations.
2.
The installation should be designed to work with flow
temperatures of up to 86
o
C.
3.
All components of the system must be suitable for a working
pressure of 3 bar and a maximum design temperature of 110
o
C.
Extra care should be taken in making all connections so that the
risk of leakage is minimised.
The following components are incorporated within the appliance:
a.
Circulating pump.
b.
Safety valve, with a non-adjustable preset lift pressure of 3
bar.
c.
Pressure gauge, covering a range of 0 to 4 bar.
d.
An 8-litre expansion vessel, with an initial charge pressure
of 0.75 bar.
4.
‘Make-up’ Water.
Provision must be made for replacing water
loss from the system, either :
a.
From a manually filled ‘make-up’ vessel with a readily visible
water level. The vessel should be mounted at least 150mm
above the highest point of the system and be connected
through a non-return valve to the system, fitted at least
150mm below the ‘make-up’ vessel on the return side of
the radiators.
or
b.
Where access to a ‘make-up’ vessel would be difficult, by
pre-pressurisation of the system.
The maximum cold water capacity of the system should
not exceed 143 litres. This is the maximum system
volume for the boiler expansion vessel. If the capacity of
the vessel is not considered sufficient for this, or for any
other reason, an additional vessel
MUST
be installed on
the return to the boiler.
Guidance on vessel sizing is given in table opposite.
5. Filling
The system may be filled by the following method:
Through a temporary hose connection from a ‘draw-off’ tap,
supplied from a service pipe under mains pressure. Where the
mains pressure is excessive, a pressure reducing valve must be
used to facilitate filling. When installing the filling device, it must
be connected as below to fully comply with the water regulations.
This may involve the fitting of an additional WRAS approved
isolator valve to the mains supply.
i. Thoroughly flush out the whole system with cold water.
ii. Fill and vent the system until the pressure gauge registers 1.5
bar, and examine for leaks.
iii. Check the operation of the safety valve by raising the water
pressure until the valve lifts. This should occur within 0.3 bar
of the preset lift pressure.
iv. Release water from the system until the minimum system
design pressure is reached; 1.0 bar if the system is to be pre-
pressurised.
Notes
a.
The method of filling, refilling, topping up or flushing sealed primary
hot water circuits from the mains via a temporary hose connection
is only allowed if acceptable to the local water authority.
b.
Antifreeze fluid, corrosion and scale inhibitor fluids suitable for use
with boilers having aluminium heat exchangers may be used in the
central heating system.
1.14 SYSTEM REQUIREMENTS - Central Heating
Safety valve setting
bar
3.0
Vessel charge pressure
bar
0.5 to 0.75
System pre-charge pressure
bar
None
1.0
System volume
Expansion vessel
(litres)
volume (litres)
25
1.6
1.8
50
3.1
3.7
75
4.7
5.5
100
6.3
7.4
125
7.8
9.2
150
9.4
11.0
175
10.9
12.9
190
11.9
14.0
200
12.5
14.7
250
15.6
18.4
300
18.8
22.1
For other system volumes
multiply by the factor across
0.063
0.074
CH Return
Ecl 6053
Hose unions
Mains
water supply
Temporary hose
(disconnect after filling)
Additional
stop valve
Double check valve
assembly
(
note direction of flow
)
Summary of Contents for System s30
Page 4: ...4 Installation and Servicing ...
Page 6: ...6 Installation and Servicing ...
Page 58: ......